Walla Walla Header Image

Walla Walla District

Home
Home > Media > News Releases

News Releases by Month

October 2018 (5)
September 2018 (15)
August 2018 (18)
July 2018 (15)
June 2018 (13)
May 2018 (14)
April 2018 (10)
March 2018 (10)
February 2018 (14)
January 2018 (4)
December 2017 (4)
November 2017 (8)
October 2017 (4)
September 2017 (10)
August 2017 (14)
July 2017 (5)
June 2017 (9)
May 2017 (15)
April 2017 (12)
March 2017 (26)
February 2017 (6)
January 2017 (12)
December 2016 (12)
November 2016 (6)
October 2016 (6)
September 2016 (8)
August 2016 (9)
July 2016 (8)
June 2016 (16)
May 2016 (10)
April 2016 (8)
March 2016 (7)
February 2016 (6)
January 2016 (1)
December 2015 (1)
November 2015 (5)
October 2015 (5)
September 2015 (12)
August 2015 (8)
July 2015 (6)
June 2015 (8)
May 2015 (5)
April 2015 (4)
March 2015 (9)
February 2015 (8)
January 2015 (7)
December 2014 (4)
November 2014 (11)
October 2014 (5)
September 2014 (12)
August 2014 (10)
July 2014 (9)
June 2014 (6)
May 2014 (12)
April 2014 (6)
March 2014 (10)
February 2014 (9)
January 2014 (3)
December 2013 (3)
November 2013 (4)
October 2013 (6)
September 2013 (7)
August 2013 (5)
July 2013 (8)
June 2013 (4)
May 2013 (13)
April 2013 (5)
March 2013 (8)
February 2013 (9)
January 2013 (5)
December 2012 (6)
November 2012 (8)
October 2012 (7)
September 2012 (8)
August 2012 (6)
July 2012 (8)
June 2012 (14)
May 2012 (16)
April 2012 (13)
March 2012 (12)
February 2012 (8)
January 2012 (3)
December 2011 (6)
November 2011 (7)
October 2011 (13)
September 2011 (14)
August 2011 (11)
July 2011 (11)
June 2011 (35)
May 2011 (21)
April 2011 (11)
March 2011 (9)
February 2011 (20)
January 2011 (7)

Bookmark and Share Email Print

Posted 8/10/2018

Release no. 18-089


Contact
CENWW-PA
5095277020
CENWW-PA@USACE.ARMY.MIL

WALLA WALLA, Wash. – Contractors will begin work Monday, Aug. 13, to remove about 350 cubic yards of silt deposits from the interior of the Mill Creek Project diversion dam, located about 2 miles east of Walla Walla, Washington, requiring temporary and/or intermittent access closures to land areas near the work zone, U.S. Army Corps of Engineers officials announced today. 

The Corps awarded a contract, valued at about $142,000, to Lanterra LLC, a registered small, disadvantaged, minority-owned business in Houston, Texas, to perform the work, which is expected to require about two to three weeks to complete.

Access to recreation areas and the Mill Creek Trail should not be significantly affected by the work activity. However, there could be short-duration, intermittent closures on the south levee service road near the diversion dam and along the diversion canal for visitor safety while construction vehicles maneuver near the work site. 

Visitors should be aware of construction vehicles and trucks entering and exiting the work site at the diversion dam and traveling to and from the sediment disposal site on the downstream side on the Bennington Lake storage dam. Trucks will be transporting sediment from both ends of the diversion dam, via Rooks Park on the north end, traveling along Mill Creek Road, Tausick Way and up Reservoir Road; and on the south end, traveling along Corps service roads and around the east side of the lake. This additional traffic will continue throughout the work period. 

A graphic-map of the construction area is available on the Walla Walla District’s website www.nww.usace.army.mil.

For more information about this project or for general information about Mill Creek Dam and Bennington Lake, call the Mill Creek office at 509-527-7160.
###