|
Mill Creek Flood Control Project New Office and Maintenance Buildings
Mill Creek Project
Walla Walla, Washington
Environmental Assessment (EA) and draft Finding of No Significant Impact (FONSI)
The U.S. Army Corps of Engineers, Walla Walla District (Corps) proposes to construct new office and maintenance buildings, along with undertaking other support activities including the installation of new utilities, landscaping, new parking area, new vehicle shed, new public restroom and new footbridge.
The Corps will wait for completion of a scheduled 15-day public review period being provided for the EA and draft FONSI. If no comments are received during this time that are determined to be of a significant nature, the Corps will finalize the EA and sign the FONSI as its National Environmental Policy Act (NEPA) compliance for the Mill Creek Flood Control Project New Office and Maintenance Buildings. This will conclude the Corps' review requirements under NEPA.
Comments should be postmarked, faxed, or e-mailed by Sept. 2, 2011. Comments may be mailed to
Walla Walla District, Corps of Engineers
Environmental Compliance Section
ATTN: John Leier
201 North Third Avenue
Walla Walla, WA 99362-1876
Comments may be faxed to MillCreekDraftEA@usace.army.mil. If you have any questions or need additional information, please contact Mr. Leier at 509-527-7269.
To see the EA, click here.
To see the FONSI, click here.
|