Extract From the Annual Report of the
Chief
of Engineers, 1950
Department of the Army
Office of the Chief of Engineers
1951
REQUIREMENTS OF LOCAL COOPERATION FOR FLOOD-CONTROL PROJECTS
Improvements
Navigation
| 1. 2. 3. 4. 5. |
Snake River, Oreg., Wash., and Idaho McNary Lock and Dam, Columbia River, Oreg. Umatilla Harbor, Oreg. Examinations, surveys, and contingencies (general) Plant allotment |
NAVIGATION
1. SNAKE RIVER, OREG., WASH., AND IDAHO
| Dam 1 | Ice Harbor, river mile 9.7 | $95,899,000 |
| Dam 2 | Lower Monumental, river mile 44.7 | 86,962,000 |
| Dam 3 | Little Goose, river mile 72.2 | 97,967,000 |
| Dam 4 | Lower Granite, river mile 113.1 | 81,977,000 |
| Total | 362,805,000 | |
| Description of Work | New Work | Maintenance |
|---|---|---|
| Site selection, lands, and damages (all dam sites) | $35,206.11 | |
| Ice Harbor Dam (dam 1) | 74,576.07 | |
| Lower Monumental Dam (dam 2) | 9.35 | |
| Maintenance of channel between Lewiston and Johnson Bar | $4,601.82 | |
| Total | $100,791.33 | $4,601.82 |
| Description of Work | New Work | Maintenance |
|---|---|---|
| Site selection, lands, and damages (all dam sites) | $583,536.58 | |
| Ice Harbor Dam (dam 1) | 683,882.11 | |
| Lower Monumental Dam (dam 2) | 43,105.84 | |
| Maintenance of channel between Lewiston and Johnson Bar | $8,820.81 | |
| Total | $1,310,584.53 | $8,820.81 |
| New work: | |
|---|---|
| Accounts payable | 8,781.83 |
| Dam 1 (Ice Harbor) | 277,077.90 |
| Continued planning | 285,859.63 |
| Total new work | 285,859.63 |
| Maintenance: | |
| Accounts payable | .15 |
| Construction of construction works and removal of boulders |
6,398.18 |
| Total maintenance | 6,398.33 |
| Total All Work | 292,257.96 |
| New work: | |
|---|---|
| Land acquisition | $205,000 |
| Construction of access facilities, water well, sewer, and water-distribution systems, and temporary office building | 105,000 |
| Initiation of design and manufacture of turbines and generators | 90,000 |
| Initiation of construction by contract of first cofferdam and work therein | 3,600,000 |
| Total new work | 4,000,000 |
| Maintenance: | |
| Maintenance of channel above Lewiston, Idaho, by Government plant and hired labor | 5,000 |
| Total All Work | 4,005,000 |
| Cost and Financial Summary | ||||||
|---|---|---|---|---|---|---|
| Fiscal year ending June 30 | Total to June 30, 1950, including fiscal years prior to 1946 | |||||
| 1946 | 1947 | 1948 | 1949 | 1950 | ||
| New Work | ||||||
| $800,000.00 | | $170,000.00 | $300,000.00 | $225,000.00 | $1,934,763.43¹ | |
| 263,035.07 | 196,130.82 | 355,716.93 | 381,865.73 | 109,791.53 | 1,745,347.96¹ | |
| 269,399.07 | 241,110.35 | 358,678.97 | 302,470.20 | 130,092.71 | 1,736,514.73¹ | |
| Maintenance | ||||||
| | 5,000.00 | | -780.01 | 6,000.00 | 214.946.70 | |
| | 156.29 | 4,062.70 | | 4,601.82 | 213,548.52 | |
| | 135.45 | 4,083.54 | | 4,601.67 | 213,548.37 | |
| ¹Does not include $85,000.00 contributed funds expended for new work on previous projects. | ||||||
| Other new work data: | |
|---|---|
| Unobligated balance, June 30, 1950 | $184,977.58 |
| 87,610.93 | |
| 272,588.51 | |
| 361,217,389.07 | |
2. McNARY LKOCK AND DAM, COLUMBIA RIVER, OREG.
| Navigation Lock | |
|---|---|
| Type | Single lift |
| Dimensions: | |
| Net clear width of chamber | 86 feet |
| Net clear length | 675 feet |
| Lift (vertical): | |
| At extreme low water and normal pool | 92 feet |
| At mean annual flow (190,000 cubic feet per second) | 84.4 feet |
| At average maximum flow (550,000 cubic feet per second) | 72.3 |
| Depth over miter sill at adopted low water (43,000 cubic feet per second) | 12 feet |
| Depth over upper sill at normal pool (elevation 340) | 20 feetD |
| Character of foundation | Basalt flow |
| Spillway Dam | |
| Over-all length of spillway dam section | 1,310 |
| Type of construction | Concrete gravity |
| Elevation spillway crest | 291 feet above mean sea level |
| Elevation deck | 361 feet above mean sea level |
| Height, maximum (foundation to deck) | 158 feet |
| Type of control | Fixed wheel segmental lift gates |
| Number of gates | 22 |
| Size of gates | 50 by 53 feet |
| Stilling basin type | Concrete apron with baffles |
| Normal pool elevation | 340 feet above mean sea level |
| Maximum pool elevation | 356.5 feet above mean sea level |
| Maximum spillway capacity at normal pool elevation | 1,480,000 cubic feet per second |
| Maximum spillway capacity at maximum pool elevation | 2,200,000 cubic feet per second |
| Accounts payable | $2,718,693.93 |
| Engineering, hired labor | 1,479,831.00 |
| Engineering, contracts | 70,169.00 |
| Lands | 3,898,810.00 |
| Operations of facilities | 3,898,810.00 |
| Miscellaneous items of construction by hired labor | 89,000.00 |
| Supply contracts: | |
| Powerhouse equipment (governing equipment, hydraulic turbines, generators, transformers, control equipment, station services switch gear, cranes, etc.) | 6,285,475.03 |
| Equipment and material for lock, spillway and fishways (sheet-steel piling, slide gates and operating machinery, gantry cranes, tainter valves and operating machinery, culvert bulkheads and trash racks, spillway gates, derricks, miter gates and stop logs, bascule bridges, etc.) | 1,852,000.00 |
| Construction of a portion of navigation lock, abutment, fishways, spillway, dam, etc., by contract | 1,119,418.00 |
| Construction of second-step cofferdam, substructure for two main units, station-service bay and assembly bay of powerhouse, and portion of Oregon shore fishways, by contract | 12,980,000.00 |
| Construction of McNary powerhouse, spillway, Oregon shore fishladder, and appurtenant structures | 1,371,000.00 |
| Construction of McNary levees, by contract | 610,000.00 |
| Relocation of railroads, highways, and utilities, by several contracts | 20,803,000.00 |
| Buildings and grounds | 620,000.00 |
| Total | 54,642,396.96 |
| Engineering | $1,000,000 |
| Continuing contract for completion of spillway, powerhouse, abutments, and fish passing facilities | 20,221,000 |
| Construction of McNary levees | 5,050,000 |
| Continue manufacture of equipment for powerhouse | 8,953,000 |
| Continue land acquisition | 3,000,000 |
| Continue relocations | 5,697,000 |
| Buildings and grounds, by contract | 630,000 |
| Continue ferry operation, camp maintenance, school facilities, etc. | 500,000 |
| Miter gates, spillway gates, bascule bridge, valves, cranes, derricks, miscellaneous equipment | 949,000 |
| Total | 46,000,000 |
| Cost and Financial Summary | ||||||
|---|---|---|---|---|---|---|
| Fiscal year ending June 30 | Total to June 30, 1950, including fiscal years prior to 1946 | |||||
| 1946 | 1947 | 1948 | 1949 | 1950 | ||
| New Work | ||||||
| $3,000,000.00 | | $4,500,000.00 | $30,000,000.00 | $35,000,000.00 | $72,575,000.00 | |
| 410,329.50 | 906,053.22 | 5,96,213.69 | 14,336,311.20 | 36,791,572.86 | 58,377,108.16 | |
| 434,473.83 | 918,401.46 | 5,935,626.15 | 14,112,040.70 | 36,142,060.90 | 57,542,603.04 | |
| Maintenance | ||||||
| | | | - | | | |
| | | | | | | |
| | | | | | | |
| Other new work data: | |
|---|---|
| Unobligated balance, June 30, 1950 | |
| Appropriated for fiscal year ending June 30, 1951 | $39,610,000 |
| Unobligated balance available for fiscal year 1951 | 39,610,000 |
| Estimated additional amount needed to be appropriated for completion of existing project | 157,815,000 |
3. UMATILLA HARBOR, OREGON
4. EXAMINATIONS, SURVEYS, AND CONTINGENCIES (GENERAL)
| Cost and Financial Summary | ||||||
|---|---|---|---|---|---|---|
| Fiscal year ending June 30 | Total to June 30, 1950, including fiscal years prior to 1946 | |||||
| 1946 | 1947 | 1948 | 1949 | 1950 | ||
| New Work | ||||||
| | | | | | | |
| | | | | | | |
| | | | | | | |
| Maintenance | ||||||
| | | | -$20,300.00 | $16,000.00 | $36,300.00 | |
| | | | 7,095.76 | 26,114.92 | 33,210.68 | |
| | | | 7,430.54 | 25,368.10 | 32,798.64 | |
5. PLANT ALLOTMENT, WALLA WALLA, WASH., DISTRICT
| Cost and Financial Summary | ||||||
|---|---|---|---|---|---|---|
| Fiscal year ending June 30 | Total to June 30, 1950, including fiscal years prior to 1946 | |||||
| 1946 | 1947 | 1948 | 1949 | 1950 | ||
| New Work | ||||||
| | | | | $ | | |
| | | | | | | |
| | | | $-973,082.71 | $669,471.56 | -$303,611.15 | |
| Maintenance | ||||||
| | | | - | | | |
| | | | | | | |
| | | | | | | |
| Other new work data: Unobligated balance, June 30, 1950 | $200,402.54 | |||||
| Status of All Investigations for Navigation Called
For By River and Harbor Acts and Committee Resolutions | ||||
|---|---|---|---|---|
| Locality | Authorization Act | Date Transmitted To Congress |
Document No. |
Recommendation |
| Clearwater, Snake, and Salmon Rivers, Oreg. and Idaho (supp. 308 report). | Sec. 6, River and Harbor Act, Aug. 30, 1935. | | | |
| Columbia and Snake Rivers, Oreg., Wash., and Idaho, for further improvement in the vicinity of Umatilla, Oreg. | Senate Public Works Committee resolution, Jan. 28, 1947. | | | |
| Salmon, Snake, and Clearwater Rivers, Oreg. and Idaho (supp. 308 report). | Sec. 6, River and Harbor Act, Aug. 30, 1935. | | | |
| Snake and Columbia Rivers, Oreg., Wash., and Idaho for further improvement in the vicinity of Umatilla, Oreg. | Senate Public Works Committee resolution, Jan. 28, 1947. | | | |
| Snake, Clearwater, and Salmon Rivers, Oreg. and Idaho (supp. 308 report). | Sec. 6, River and Harbor act, Aug. 30, 1935. | | | |
| Umatilla, Oreg., for further improvement of the Columbia and Snake Rivers, Oreg., Wash., and Idaho, in vicinity of. | Senate Public Works Committee resolution, Jan. 28, 1947. | | | |
6. Columbia River Basin, Local Flood Protection Projects, Walla Walla District
7. Jackson Hole, Snake River, Wyo.
8. Heise-Roberts Area, Snake River, Idaho
| Accounts payable | $12,492.00 |
| Complete construction of levee and bank protection and revetting of unrevetted levees | 180,729.37 |
| Total | 193,221.37 |
|---|
| Cost and Financial Summary | ||||||
|---|---|---|---|---|---|---|
| Fiscal year ending June 30 | Total to June 30, 1950, including fiscal years prior to 1946 | |||||
| 1946 | 1947 | 1948 | 1949 | 1950 | ||
| New Work | ||||||
| $250,000.00 | | $5,000.00 | $351,000.00 | $340,000.00 | $1,490,000.00 | |
| 27,103.36 | $78,492.06 | 539,252.80 | 453,750.74 | 207,792.18 | 1,306,391.14 | |
| 23,423.68 | 78,257.70 | 519,916.47 | 468,693.87 | 209,383.56 | 1,299,675.28 | |
| Maintenance | ||||||
| | | | - | | | |
| | | | | | | |
| | | | | | | |
| Other new work data: Unobligated balance, June 30, 1950 | $73,917.19 | |||||
9. Lucky Peak Reservoir, Boise River, Idaho
| Accounts payable | $147,174.31 |
| Engineering hired labor | 335,904.00 |
| Engineering contracts | 39,541.00 |
| Acquisition of reservoir lands | 374,299.00 |
| Construction of outlet tunnel by contract | 929,835.00 |
| Construction of embankment by contract | 1,298,984.00 |
| Relocations | 1,298,984.00 |
| Total | 4,728,560.05 |
|---|
| Engineering | $175,000 |
| Continue construction of embankment by contract | 1,300,000 |
| Construction of spillway, intake, and control | 850,000 |
| Relocations | 3,768,000 |
| Revisions to Arrowrock Dam | 50,000 |
| Miscellaneous construction by contract | 107,000 |
| Total | 6,250,000 |
|---|
| Cost and Financial Summary | ||||||
|---|---|---|---|---|---|---|
| Fiscal year ending June 30 | Total to June 30, 1950, including fiscal years prior to 1946 | |||||
| 1946 | 1947 | 1948 | 1949 | 1950 | ||
| New Work | ||||||
| | | $190,000.00 | $590,000.00 | $3,000,000.00 | $3,780,000.00 | |
| | | 158,065.85 | 339,844.79 | 1,099,374.91 | 1,597,285.55 | |
| | | 152,867.01 | 383,417.65 | 921,826.90 | 1,458,111.56 | |
| Maintenance | ||||||
| | | | - | | | |
| | | | | | | |
| | | | | | | |
| Other new work data: | ||||||
| $6,671.61 | ||||||
| 2,400,000.00 | ||||||
| 2,406,671.61 | ||||||
| 15,820,000.00 | ||||||
10. Lewiston-Clarkston Levees
11. Pullman, Palouse River, Wash.
| Cost and Financial Summary | ||||||
|---|---|---|---|---|---|---|
| Fiscal year ending June 30 | Total to June 30, 1950, including fiscal years prior to 1946 | |||||
| 1946 | 1947 | 1948 | 1949 | 1950 | ||
| New Work | ||||||
| $5,000.00 | | | $10,000.00 | $11,000.00 | $46,000.00 | |
| $8,334.72 | $144.88 | $2,914.09 | 12,986.89 | 11,113.49 | 35,545.67 | |
| | | 2,840.73 | 12,986.89 | 11,113.49 | 35,026.67 | |
| Maintenance | ||||||
| | | | - | | | |
| | | | | | | |
| | | | | | | |
| Other new work data: | ||||||
| $10,373.33 | ||||||
| 15,000.00 | ||||||
| 25,373.33 | ||||||
| 1,159,000.00 | ||||||
12. Colfax, Palouse River, Wash.
| Cost and Financial Summary | ||||||
|---|---|---|---|---|---|---|
| Fiscal year ending June 30 | Total to June 30, 1950, including fiscal years prior to 1946 | |||||
| 1946 | 1947 | 1948 | 1949 | 1950 | ||
| New Work | ||||||
| $5,000.00 | | $10,000.00 | $15,000.00 | $25,000.00 | $80,000.00 | |
| $25,120,78 | $-33.41 | $5,760.57 | $24,113.86 | $4,585.74 | $59,585.74 | |
| $24,450.32 | $675.25 | $5,571.96 | $24,302.47 | $4,443.39 | $59,443.99 | |
| Maintenance | ||||||
| | | | - | | | |
| | | | | | | |
| | | | | | | |
| Other new work data: | ||||||
| $14,556.01 | ||||||
| $14,556.01 | ||||||
| $2,088,000.00/TD> | ||||||
13. Mill Creek, Wash.
| Accounts payable | 184.48 |
| Installation of piezometers along Mill Creek Channel | 3,000.00 |
| Reserve for damage claims or flowage easements for seepage areas below the dam | 5,750.08 |
| Available for revocation and reallotment to other flood-control projects | 90,700.00 |
| Total new work | 99,634.56 |
|---|
| Accounts payable | 8,684.72 |
| Operation | 1,300,000 |
| Maintenance of grounds and structures | 850,000 |
| Weed control | 3,768,000 |
| Reservoir operation studies | 50,000 |
| Cooperative stream gaging | 107,000 |
| Reading piezometers | 1,000.00 |
| Completion of improvements and reconstruction | 28,419.02 |
| Total Maintenance | 57,753.74 |
|---|---|
| Total All Work | 157,388.30 |
| Cost and Financial Summary | ||||||
|---|---|---|---|---|---|---|
| Fiscal year ending June 30 | Total to June 30, 1950, including fiscal years prior to 1946 | |||||
| 1946 | 1947 | 1948 | 1949 | 1950 | ||
| New Work | ||||||
| $125,500.00 | -15,000.00 | | $559,900.00 | $58,800.00 | $2,257,594.66¹ | |
| 1,247.85 | 5,191.37 | $19,168.70 | 592,819.58 | 36,432.79 | 2,158,144.58¹ | |
| 1,238.45 | 5,092.65 | 36,876.68 | 575,143.66 | 36,324.37 | 2,157,960.10¹ | |
| Maintenance | ||||||
| 15,000.00 | | 17,500.00 | 251,000.00 | 18,000.00 | 300,900.00 | |
| 11,216.72 | 11,119.68 | 11,922.65 | 50,288.63 | 196,695.80 | 324,830.98 | |
| 11,972.78 | 11,597.90 | 12,076.40 | 213,059.09 | 25,420.84 | 316,175.28 | |
| Other new work data: | ||||||
| $99,103.16 | ||||||
| 1Does not include $80,000 Contributed funds expended for new work. | ||||||
14. Milton-Freewater, Walla Walla River, Oreg.
| Accounts payable | 27,017.21 |
| Construction of levee and channel improvement | 531,544.16 |
| Total | $558,561.37 |
|---|
| Cost and Financial Summary United States Funds | ||||||
|---|---|---|---|---|---|---|
| Fiscal year ending June 30 | Total to June 30, 1950, including fiscal years prior to 1946 | |||||
| 1946 | 1947 | 1948 | 1949 | 1950 | ||
| New Work | ||||||
| | | | $300,000.00 | $640,000.00 | $1,015,000.00 | |
| 12,311.03 | $2,037.50 | $5,528.53 | 49,542.26 | 388,853.04 | 487,455.84 | |
| 12,222.61 | 2,223.28 | 5,410.53 | 225,161.71 | 186,334.38 | 460,438.63 | |
| Maintenance | ||||||
| | | | - | | | |
| | | | | | | |
| | | | | | | |
| Other new work data: | ||||||
| $206,283.39 | ||||||
| Cost and Financial Summary Contributed Funds | ||||||
|---|---|---|---|---|---|---|
| Fiscal year ending June 30 | Total to June 30, 1950, including fiscal years prior to 1946 | |||||
| 1946 | 1947 | 1948 | 1949 | 1950 | ||
| New Work | ||||||
| | | | | $6,300.00 | $6,300.00 | |
| | | | | 2,300.00 | 2,300.00 | |
| | | | | 2,300.00 | 2,300.00 | |
| Maintenance | ||||||
| | | | - | | | |
| | | | | | | |
| | | | | | | |
15. Dayton, Touchet River, Wash.
| Cost and Financial Summary | ||||||
|---|---|---|---|---|---|---|
| Fiscal year ending June 30 | Total to June 30, 1950, including fiscal years prior to 1946 | |||||
| 1946 | 1947 | 1948 | 1949 | 1950 | ||
| New Work | ||||||
| $5,000.00 | $700.00 | $5,000.00 | | | $20,300.00 | |
| 12,635.52 | 124.75 | 666.49 | $141.28 | | 16,063.99 | |
| 12,875.35 | 190.41 | 662.49 | 145.28 | | 10,063.99 | |
| Maintenance | ||||||
| | | | - | | | |
| | | | | | | |
| | | | | | | |
| Other new work data: | ||||||
| $4,236.01 | ||||||
| 455,936.00 | ||||||
16. Pendleton, Umatilla River, Oreg.
17. Emergency Flood-Control Work Under Authority of the Flood Control Act Approved July 24, 1946
| Cost and Financial Summary | ||||||
|---|---|---|---|---|---|---|
| Fiscal year ending June 30 | Total to June 30, 1950, including fiscal years prior to 1946 | |||||
| 1946 | 1947 | 1948 | 1949 | 1950 | ||
| New Work | ||||||
| | | | $55,600.00 | $11,807.03 | $43,792.97 | |
| | | | 28,290.51 | 10,473.44 | 38,763.95 | |
| | | | 20,179.22 | 18,534.73 | 38,713.95 | |
| Maintenance | ||||||
| | | | - | | | |
| | | | | | | |
| | | | | | | |
| Other new work data: | ||||||
| $4,929.02 | ||||||
18. Emergency Flood-Control Work Under Authority of Public Laws 138 and 318,
Seventy-Eighth Congress; Public Law 75, Seventy-Ninth Congress;
| Cost and Financial Summary | ||||||
|---|---|---|---|---|---|---|
| Fiscal year ending June 30 | Total to June 30, 1950, including fiscal years prior to 1946 | |||||
| 1946 | 1947 | 1948 | 1949 | 1950 | ||
| New Work | ||||||
| | | | | | | |
| | | | | | | |
| | | | | | | |
| Maintenance | ||||||
| $131,000.00 | $31,000.00 | $204,546.58 | $651,500.00 | $136,512.84 | $1,772,799.42 | |
| 175,742.68 | 53,654.84 | 157,326.27 | 484,161.95 | 182,721.75 | 1,601,172.01 | |
| 197,499.45 | 57,792.03 | 166,270.69 | 142,653.89 | 475,716.18 | 1,561,488.89 | |
19. Emergency Flood-Control, Work Under Authority Section 205 of Public Law 858, Eightieth Congress
| Cost and Financial Summary | ||||||
|---|---|---|---|---|---|---|
| Fiscal year ending June 30 | Total to June 30, 1950, including fiscal years prior to 1946 | |||||
| 1946 | 1947 | 1948 | 1949 | 1950 | ||
| New Work | ||||||
| | | $190,000.00 | $590,000.00 | $3,000,000.00 | $3,780,000.00 | |
| | | 158,065.85 | 339,844.79 | 1,099,374.91 | 1,597,285.55 | |
| | | 152,867.01 | 383,417.65 | 921,826.90 | 1,458,111.56 | |
| Maintenance | ||||||
| | | | - | | | |
| | | | | | | |
| | | | | | | |
| Other new work data: | ||||||
| $6,671.61 | ||||||
| 2,400,000.00 | ||||||
| 2,406,671.61 | ||||||
| 15,820,000.00 | ||||||
20. Emergency Flood-Control Work Under Authority of the Flood Control Act Approved August 18, 1941
| Cost and Financial Summary | ||||||
|---|---|---|---|---|---|---|
| Fiscal year ending June 30 | Total to June 30, 1950, including fiscal years prior to 1946 | |||||
| 1946 | 1947 | 1948 | 1949 | 1950 | ||
| New Work | ||||||
| | | | | | | |
| | | | | | | |
| | | | | | | |
| Maintenance | ||||||
| $35,300.00 | $361,000.00 | $2,953.42 | $90,000.00 | | $489,253.42¹ | |
| 261.28 | 354,638.38 | 25,992.95 | 71,845.89 | $31,442.15 | $484,180.65¹ | |
| | 350,510.63 | 22,030.98 | 80,196.09 | .80 | 452,738.00¹ | |
| ¹Does not include $20,000 contributed funds expended for emergency repairs at Silver Bridge, Boise | ||||||
21. Preliminary Examinations, Surveys, and Contingencies for Flood Control
| Cost and Financial Summary | ||||||
|---|---|---|---|---|---|---|
| Fiscal year ending June 30 | Total to June 30, 1950, including fiscal years prior to 1946 | |||||
| 1946 | 1947 | 1948 | 1949 | 1950 | ||
| New Work | ||||||
| | | | | | | |
| | | | | | | |
| | | | | | | |
| Maintenance | ||||||
| $16,354.72 | $35,659.40 | $18,481.33 | $86,158.19 | $117,600.00 | $363,526.40 | |
| 16,354.72 | 35,659.40 | 18,481.33 | 55,007.52 | 146,996.36 | 361,780.28 | |
| 16,354.72 | 35,659.40 | 18,481.33 | 44,742.25 | 154,448.41 | 358,958.87 | |
22. Inactive Flood-Control Projects
| Name of project | For last full Report see Annual Report for | Cost and expenditures to June 30, 1950 | Estimated amount required to Complete | |
|---|---|---|---|---|
| New work | Maintenance | |||
| Pendleton, Umatilla River, Oreg. | 1939 | $143,262.83 | | (1) |
| Malheur Improvement District near Weiser, Snake River, Idaho | 1949 | 319.39 | | (2 4) $41,900 |
| Pilot Rock, Birch Creek, Oreg. | 1949 | 3,700.00 | | (3) 122,300 |
| Snagging and Clearing under authority of section 2 of Flood Control Act approved Aug. 28, 1937, as amended | 1949 | 106,861.05 | | (1) |
|
(1) Completed (2) No work scheduled until fiscal year 1954. (3) Indefinitely deferred pending development of a plan that will meet requirements of local interests. (4) The estimated amount required to complete will be increased by $980, due to Revocation of this Amount in fiscal year 1951. The total required will then be $42,880. | ||||
| Locality | Authorization act | Date transmitted to Congress | Document No. | Recommendation |
|---|---|---|---|---|
| Big Wood River and tributaries, Blaine County, Idaho, Snake River and tributaries, with a view of flood protection on. | Senate Public Works Committee resolution, Apr. 20, 1948. | |||
| Boise River, Idaho | Commerce Committee resolution, Oct. 12, 1943 |
Feb. 14, 1950 | H. Doc. 531, 81st Cong., 2d sess. |
Favorable |
| Boise River, Idaho, to provide flood protection along Dry Creek, Idaho. | Senate Public Works Committee resolution, Mar. 4, 1947. | |||
| Boise River and tributaries, Idaho, flood control | Flood Control Committee resolution, Nov. 10, 1943. | Feb. 14, 1950. | H. Doc. 531, 81st Cong., 2d Sess. | Do. |
| Cascade storage project, Payette River, Idaho. | Flood Control Act, Mar. 4, 1937. | |||
| Clearwater River, (Snake, Clearwater and Salmon Rivers), Oreg., and Idaho (supp.308) | Sec. 6, River and Harbor Act, Aug. 30, 1935. | |||
| Columbia River and tributaries, review of 308 report. | Commerce Committee resolution, Sept. 24, 1943. | Feb. 14, 1950. | H. Doc. 531, 81st Cong., 2d Sess. | Do. |
| Dry Creek, Boise River, Idaho, to provide flood protection. | Senate Public Works Committee resolution, Mar. 4, 1947. | |||
| Grande Ronde River and tributaries, Oreg. | Flood Control Act, Aug. 28, 1937. | |||
| Grande Ronde River and tributaries, Oreg. | Flood Control Act, Mar. 4, 1937. | |||
| Flood Control Act, June 13, 1934. | ||||
| Heise-Roberts Area, Idaho, Snake River, Idaho. | Commerce Committee resolution, Sept. 24, 1943. | |||
| Marsh Creek, and along Portneuf River, Idaho, in the Pocatello area, Snake River Basin, for flood protection. | Flood Control Committee resolution, July 23, 1946. | |||
| Marsh Creek and Portneuf River, Idaho, in the Pocatello area, Snake River Basin, for flood protection. | Commerce Committee resolution, July 27, 1946. | |||
| Mill Creek, Wash. for flood protection, at Walla Walla, Wash. | Commerce Committee resolution, Mar. 5, 1946. | |||
| Palouse and Touchet Rivers, Wash. | House Public Works Committee resolution, July 6, 1949. | |||
| Palouse River, Idaho, Wash., and Oregon. | Senate Public Works Committee resolution, April 15, 1949. | |||
| Payette River, Idaho | Flood Control Act, Mar. 4, 1937. | |||
| Payette River, Idaho, Cascade storage project. | Flood Control Act, Mar. 4, 1937. | |||
| Pocatello Area, Portneuf River, and along Marsh Creek, Idaho, Snake River Basin for flood protection. | Flood Control Committee resolution, July 23, 1946. | |||
| Commerce Committee resolution, July 27, 1946. | ||||
| Portneuf River in the Pocatello area, and along Marsh Creek, Idaho, Snake River Basin for flood protection. | Flood Control Committee resolution, July 23, 1946. | |||
| Commerce Committee resolution, July 27, 1946. | ||||
| Powder River and tributaries, Oreg. | Flood control Act, Aug. 28, 1937. | |||
| Powder River, Oreg. | Flood Control Act, Mar. 4, 1937. | |||
| Salmon River, Oreg., Snake, Clearwater and Salmon Rivers, Oreg., and Idaho (supp. 308) | Sec. 6, River and Harbor Act, Aug. 30, 1935. | |||
| Snake River and tributaries, with a view to flood protection on Big Wood River and tributaries, Blaine County, Idaho. | Senate Public Works Committee resolution, Apr. 20, 1948. | |||
| Snake River Basin, Heise-Roberts area, Idaho. | Commerce Committee resolution, Sept. 24, 1943. | |||
| Snake River Basin, (partial report on Columbia River and tributaries) | Commerce Committee resolution, Sept. 24, 1943. | |||
| Snake River Basin, for flood protection along Portneuf River, Idaho, in the Pocatello area, and along Marsh Creek, Idaho. | Flood Control Committee resolution, July 23, 1946. | |||
| Snake River Basin, for flood protection along Portneuf River, Idaho, in the Pocatello area, and along Marsh Creek, Idaho. | Commerce Committee resolution, July 27, 1946. | |||
| Snake River and tributaries, Wyoming, flood control and bank erosion, protection in vicinity of Wilson, Wyo. | Flood Control Committee resolution, Nov. 10, 1943. | |||
| Snake, Clearwater and Salmon Rivers, Oreg., and Idaho (supp. 308). | Sec. 6, River and Harbor Act, Aug. 30, 1935. | |||
| Touchet River, Wash. | Senate Public Works Committee resolution, Apr. 15, 1949. | |||
| Touchet and Palouse Rivers, Wash. | House Public Works Committee resolution, July 6, 1949. | |||
| Umatilla River, Oreg. | Commerce Committee resolution, Mar. 23, 1939. | |||
| Walla Walla, Mill Creek, Wash., for flood protection of. | Commerce Committee resolution, Mar. 5, 1946. | |||
| Weiser River, Idaho | Flood Control Act, Mar. 4, 1937. | |||
| Wilson, Snake River and tributaries Wyoming, flood control and bank erosion protection in vicinity of. | Flood Control Committee resolution, Nov. 10, 1943. | |||