Report Upon the Improvement of Rivers and Harbors in
The Walla Walla, Wash., District

Extract From the Annual Report of the
Chief of Engineers, 1963

Department of the Army
Office of the Chief of Engineers
1963


This district comprises southeastern Washington, exclusive of the watershed of the Columbia River and tributaries above and including the Yakima River, Wash.; all of Idaho, except northern part and a small southeastern portion; a portion of western Wyoming; a small part of northwestern Utah; part of northeastern Nevada and all of eastern Oregon.

Improvements

Navigation
1.
2.
3.
4.
5.
6.
7.
8.
9.
Snake River, Oreg., Wash., and Idaho
Lower Granite Lock and Dam, Snake River, Wash.
Little Goose Lock and Dam, Snake River, Wash.
Lower Monumental Lock and Dam, Snake River, Wash.
Ice Harbor Lock and Dam, Snake River, Wash.
McNary Lock and Dam, Columbia River, Oreg.
John Day Lock and Dam, Columbia River, Wash. and Oreg.
Columbia River and tributaries above Celilo Falls to Kennewick, Wash.
Other authorized navigation projects
Flood Control
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
Columbia River Basin, Local Flood Protection Projects
Jackson Hole, Snake River, Idaho
Ririe Reservoir, Willow Creek, Idaho
Blackfoot River, Columbia River Basin, Idaho
Portneuf River and Marsh Creek, Columbia River Basin, Idaho
Lucky Peak Reservoir, Boise River, Idaho
Boise Valley, Columbia River Basin, Idaho
Bruces Eddy Reservoir, North Fork Clearwater River, Idaho
Pullman, Palouse River, Wash.
Colfax, Palouse River, Wash.
Dayton, Touchet River, Wash.
Mill Creek, Washington
Pilot Rock, Birch Creek, Oreg.
John Day River, Columbia River Basin, Oreg.
Other authorized flood-control projects
Inspection of completed flood control works
Flood control work under special authorization
Scheduling of flood control operations
General investigations
28.
29.
30.
Surveys
Collection and study of basic data
Research and development


NAVIGATION

1. SNAKE RIVER, OREG., WASH., AND IDAHO

Location. The Snake River, which is the largest tributary of Columbia River, rises in Yellowstone National Park, in the western part of Wyoming, flows in a general westerly direction for about 1,000 miles and empties into Columbia River near Pasco, Wash., 324 miles from the Pacific Ocean.

Previous projects. For previous projects see Annual Reports, page 1981 for 1962, page 1991 for 1915, page 2246 for 1903, and page 1986 for 1906.

Existing Project. River and Harbor Act of March 2, 1945 (H. Doc. 704, 75th Cong., 2d sess.) authorized construction of such dams as are necessary and open channel improvements for purposes of providing slackwater navigation and irrigation between the mouth of Snake River and Lewiston, Idaho. This authorization modifies the previous authorizations only for that portion of the improvement below Lewiston, Idaho. The Acts of June 13, 1902, and August 30, 1935, as they pertain to the open river improvement from Lewiston, Idaho to Johnson Bar Landing are part of existing project.

Improvements presently included in the authorized project are as follows:

Item Estimated cost
(July 1963 Base)
Lower Granite Lock and Dam, river mile 107.5 $174,000,000
Little Goose Lock and Dam, river mile 72.2 150,000,000
Lower Monumental Lock and Dam, river mile 44.7 176,000,000
Ice Harbor Lock and Dam, river mile 9.7 $124,962,200¹
Open-river improvement, Lewiston to Johnson Bar Landing² 34,613
Total $624,996,813
¹Includes $285,000 for recreation facilities on completed projects.
²No channel dimensions specified, maintenance only.

Local Cooperation. None required.

Terminal facilities. There are six privately owned grain terminal facilities on Snake River. Four of these are on open river and limited in use for waterway shipping due to shallow channel depths. Two of the terminals are on Ice Harbor pool, one of which is under construction. There are two privately owned terminals below Ice Harbor lock and dam. In addition, there are four publicly owned marinas and nine small boat launching ramps, all open to public use. Facilities are adequate until slack water navigation is available and shipping volume increases following completion of dams now under construction above Ice Harbor.

Operations and results during fiscal year. Operations and results during fiscal year on Lower Granite, Little Goose, Lower Monumental, and Ice Harbor locks and dams are given in an individual report on each of those projects. On Snake River, Lewiston, Idaho, to Johnson Bar Landing, navigation channel markers were installed. Total costs for fiscal year were $22,445,593 for new work, and $485,323 for maintenance.

Condition at end of fiscal year. The following table summarizes the status of work under "Snake River, Oreg., Wash., and Idaho."

Project Approved
1963
Estimated
Cost
Total new
work
appropriations
to June 30, 1963
Cost to June 30, 1963 Percent
complete
Date construction started
New work Maintenance
Lower Granite Lock and Dam¹ $174,000,000² $1,290,823 $1,232,885  
Little Goose Lock and Dam¹ 150,000,000² 3,655,100 3,516,838 2 June 1963
Lower Monumental Lock and Dam¹ 176,000,000 30,323,515 29,430,728 17 June 1961
Ice Harbor Lock and Dam¹ 124,962,200³ 123,652,173 123,471,367 $628,932 99 January 1956
Survey for Navigation Aids 3,394  
Open River improvement—Lewiston to Johnson Bar landing 4 34,613 34,613 34,613 74,740 Maintenance only
Total 624,996,813 158,956,224 157,686,431 707,066  
1See individual report.
2Pro rata cost of site selection studies, preauthorization studies, and advance engineering.
3Includes $285,000 for recreation facilities on completed projects.
4No channel dimension specified.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$19,683,000 $30,502,000 $27,995,923 $19,415,000 $21,578,515 $158,956,224¹
Cost
19,361,853 29,104,279 29,270,049 18,126,906 22,445,593 157,686,431¹
Maintenance
Appropriated
38,800 —4,050 2,900 151,551 514,668 727,534²
Cost
25,166 9,584 2,894 150,428 485,323 707,066²
1Excludes $400,150 for new work on previous projects and contributed funds for new work consisting of $85,000 on previous projects, and $82,500 for artificial spawning channel.
2Includes $186,570 for maintenance on previous projects.

2. LOWER GRANITE LOCK AND DAM, SNAKE RIVER, WASH.

Location. The project site is located at river mile 107.5 on the Snake River at the head of the proposed Little Goose Pool, and about 33 miles downstream from Lewiston, Idaho.

Existing project. Provides for a dam, powerplant, navigation lock, and appurtenant facilities, and requires backwater levees near head of pool in the Lewiston, Idaho, Clarkston, Wash., and Asotin, Wash., areas. Improvement provides for navigation, hydroelectric power generation, recreation and incidental irrigation. Presently proposed normal pool elevation of 738 feet mean sea level would create a reservoir extending upstream about 36 miles and would provide slack-water navigation in the Lewiston-Clarkston area. Total length of dam structure will be approximately 3,100 feet. It will consist of a powerhouse, spillway dam, navigation lock, necessary nonoverflow sections, and fish passing facilities. Powerplant will be constructed for three 135,000 kilowatt units to be installed initially with provisions for three additional similar units. Spillway will provide capacity to pass a design flood of 850,000 cubic feet per second. Navigation lock will be of single-lift type and will have clear plan dimensions of 86 by 675 feet and provide a minimum depth of 15 feet over lock sills. Backwater levees will be about 9 miles long in Lewiston-Clarkston area, and 1 mile long in Asotin area.

Estimated cost for new work, revised in 1963, is $174 million. Existing project was authorized by the River and Harbor Act of March 2, 1945. (See H. Doc. 704, 75th Congress, 3d session.)

Operations and results during fiscal year. Hydrologic studies were continued and will be published in design memorandum No. 1, hydrology. Design memorandum No. 2, upper pool determination, was completed and submitted to higher authority April 16, 1963. Field data including damsite exploration and levee exploration continued and will be included in design memorandum No. 3, general design memorandum. Total costs for fiscal year were $721,916.

Condition at end of fiscal year. Design memorandum 1 is 95 percent complete and design memorandum 3 is 90 percent complete and scheduled for submission to higher authority October 1963. No construction work has been done. Total costs were $1,232,885.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
—$17,100 —$4,077 $500,000 $650,000 $1,290,823
Cost
$3,447 —2,466 326 370,146 721,916 1,232,885
Other new work data:
Unobligated balance, June 30, 1963
$4,450
Appropriated for succeeding fiscal year ending June 30, 1964
884,000
Unobligated balances available for succeeding fiscal year ending June 30, 1964
888,450
Estimated additional amount needed to be appropriated for completion of existing project
171,825,177

3. LITTLE GOOSE LOCK AND DAM, SNAKE RIVER, WASH.

Location. Site will be 70.3 miles above the mouth of the Snake River, at head of proposed Lower Monumental Pool, 40 miles north of Walla Walla, Wash., and 45 miles west of Lewiston, Idaho.

Existing project. Provides for a dam, powerplant, navigation lock and appurtenant facilities. Improvement will provide for navigation, hydroelectric-power generation and incidental irrigation. Dam will be designed for a normal pool at elevation 638 mean sea level. Normal pool will create a reservoir extending upstream about 37.2 miles and providing slack water to Lower Granite lock and dam site. Total length of dam structure will be approximately 2,660 feet. It will consist of a powerhouse, spillway dam, navigation lock, and necessary nonoverflow sections. Fish passing facilities including two ladders will be provided. Powerhouse will be constructed for three 135,000-kilowatt units to be installed initially, with provisions for three additional 135,000-kilowatt units for an ultimate installed capacity of 810,000 kilowatts. Spillway dam will provide capacity to pass a design flood of 850,000 cubic feet per second. Navigation lock will be of single lift type and have clear plan dimensions of 86 feet by 675 feet and provide a minimum depth of 15 feet over the lock sills.

Estimated cost for new work, revised in 1963, is $150,000,000. Existing project was authorized by the River and Harbor Act approved March 2, 1945. (See H. Doc. 704, 75th Cong., 3d sess.)

Operations and results during fiscal year. New work: Detailed design memoranda on all project features to be constructed in south shore contract were continued. Design memoranda for temporary project office, cofferdam, navigation lock and south shore access road were completed this fiscal year. Relocation studies, hydraulic model studies and real estate acquisitions were carried on all year. Contracts were awarded and are underway for purchase of steel sheet piling, foundation drilling at project site, exploration adits along Camas Prairie Railroad, and design and manufacture of three 212,400 horsepower hydraulic turbines. Total costs for fiscal year were $1,878,373, all for new work.

Condition at end of fiscal year. Appendix E, power studies of general design memorandum No. 2, Little Goose lock and dam was approved by Chief of Engineers subject to concurrence of Secretary of the Army. Specific design memoranda are being prepared for spillway dam, nonoverflow dams, fish facilities, highway and railroad relocations and power facilities. A construction contract was awarded for first stage construction, consisting of first step cofferdam, and diversion channel; phase I of south shore access road; and temporary project office. Construction started in June 1963 and entire project is estimated to be 2 percent complete. Total costs were $3,516,848, all for new work.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$390,100 $550,000 $715,000 $1,850,000 $3,655,100
Cost
$2,665 314,528 549,765 624,480 1,878,373 3,516,838
Other new work data:
Unobligated balance, June 30, 1963
$18,760
Appropriated for succeeding fiscal year ending June 30, 1964
9,000,000
Unobligated balances available for succeeding fiscal year ending June 30, 1964
9,018,760
Estimated additional amount needed to be appropriated for completion of existing project
137,344,900

4. LOWER MONUMENTAL LOCK AND DAM, SNAKE RIVER, WASH.

Location. Site was tentatively established at river mile 44.7 above the mouth of the Snake River at the head of Ice Harbor lock and dam pool approximately 45 miles east of Pasco, Wash. Detailed planning studies conducted in its development, establish the location of the project at river mile 41.6.

Existing project. Provides for construction of a dam, powerplant, navigation lock, relocation of railroads and highways above the proposed pool level at elevation 540 mean sea level, and appurtenant facilities, creating a slackwater pool about 30 miles long extending to the site of Little Goose lock and dam. Dam, which raises the normal water surface approximately 100 feet above the downstream Ice Harbor lock and dam pool level, will be 3,800 feet long. It will consist of an earthfill and rockfill dam at the right (north) abutment, a powerhouse, spillway dam, navigation lock and an earthfill and rockfill dam at the left (south) abutment. Powerhouse will be composed of three 135,000 kilowatt units to be installed initially and a substructure for three additional units—an ultimate total of six 135,000 kilowatt units or 810,000 kilowatts. The spillway dam will be 508 feet long, and the overflow crest at elevation 483 mean sea level will be surmounted by 8 radial gates each 50 feet wide and 60.5 feet high. This will provide capacity to pass a spillway design flood of 850,000 cubic feet per second. The deck will be at elevation 553 mean sea level and will provide a service road and track for a gantry crane. The navigation lock is a single lift type, and will have a clear plan dimension of the lock chamber 86 by 675 feet, and will provide a minimum depth of 15 feet over the lock sills. Fish passing facilities including two ladders will be provided.

The estimate of cost for new work, revised in 1963, is $176 million. The existing project was authorized by the River and Harbor Act approved March 2, 1945 (see H. Doc. 704, 75th Cong., 3d Sess.).

Operations and results during fiscal year. Construction contract for south shore construction was let during fiscal year 1962. This work included 7½ bays of spillway, south nonoverflow dam, navigation lock, south fish ladder and south abutment embankment. Work under this contract is 54 percent complete.

A supply contract for three 135,000 kilowatt turbines was let during fiscal year 1962. This was part of a contract for 15 turbine units, 12 of which are for John Day lock and dam. Work under this contract is 8 percent complete.

Part I construction of north shore access road which extends from town of Kahlotus to damsite, a distance of about 5.6 miles, was completed.

First phase construction contract which includes first-step cofferdam, initial portion of north embankment abutment, river diversion excavation, and shoofly of Northern Pacific Railway in damsite area was completed.

Construction of temporary extension of north shore access road extending from constructed portion of north shore access road, part I, to Resident Engineer's Office, a distance of about 0.6 mile, and also striping existing north shore access road was awarded and completed.

Contract for additional guardrail installation along existing north shore access road was awarded and is 54 percent complete.

Contract for installation of a wind gage on Union Pacific Railroad Co., Joso Bridge, crossing Snake River, was awarded in fiscal year 1962 and has been completed.

Work was initiated during fiscal year on construction of Union Pacific Railroad, Hinkle-Spokane main line, cofferdam bypass and Walla Walla county road relocation. This work includes 9 miles of railroad grading and 0.6 mile of county road construction. Work on this contract has just begun and is less than 1 percent complete.

A temporary agreement for relocation of Union Pacific Railroad, Hinkle-Spokane main line facilities to cofferdam bypass and shoofly No. 2 was entered into with railroad. Work covered by this agreement is about 1 percent complete.

Supply contract for procurement of 593.6 tons of sheet piling was entered into and completed. Supply contract for procurement of 4,160-volt switchgear required for installation in locks was awarded and is 29 percent complete. Supply contract for 480-volt motor control centers required for installation in locks was awarded and is 84 percent complete. Supply contract for procurement of 1,128 tons railroad rail, 6,338 cwt tie plates and 1,300 pair angle bars has been advertised and scheduled for opening July 16, 1963. This material is to be used in relocation of Union Pacific Railroad, Hinkle-Spokane main line. Supply contract for procurement of railroad ties was awarded and work is less than 1 percent complete.

Engineering studies were continued throughout the year on railroad, and county and State highway relocations; powerhouse construction and equipment installation; and studies were started on north shore construction. Work pursuant to purchase of real estate for both north and south shore reservoir requirements continued. Detailed real estate design memoranda studies are complete. Procurement of required real estate is continuing.

Total costs during the fiscal year were $18,119,159 for new work.

Condition at end of fiscal year. North shore access road, except for a short section at right abutment, is complete. South shore contract and turbine contracts delineated in the preceding subheading are 8 percent complete. Construction began in fiscal year 1961, and the entire project is 17 percent complete with total cost of $29,430,728, all for new work.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$550,000 $830,000 $1,150,000 $9,200,000 $17,913,515 $30,323,515
Cost
542,816 814,388 1,164,725 8,146,438 18,119,159 29,430,728
Other new work data:
Unobligated balance, June 30, 1963
$210,140
Appropriated for succeeding fiscal year ending June 30, 1964
20,700,000
Unobligated balances available for succeeding fiscal year ending June 30, 1964
20,910,140
Estimated additional amount needed to be appropriated for completion of existing project
124,976,485

5. ICE HARBOR LOCK AND DAM, SNAKE RIVER, WASH.

Location. On Snake River, 9.7 miles above the mouth of the river, at the head of McNary lock and dam pool, and 12 miles east of Pasco, Wash.

Existing project. Provides for construction of a dam, powerplant, navigation lock, fish ladders, appurtenant facilities, and relocation of railroads. Improvement provides for navigation, hydroelectric power generation, and incidental irrigation. Dam is designed for a normal pool at elevation 440 mean sea level. Normal pool will create a reservoir extending upstream about 31.9 miles, providing slack water to the Lower Monumental lock and dam site. Total length of structure will be approximately 2,790 feet. Beginning at south, project consists of a concrete nonoverflow section, a concrete powerhouse, a spillway dam, a concrete nonoverflow section, a navigation lock, and an earth and rock filled embankment at the north abutment. Fish passing facilities, including two ladders, will be provided. Powerplant has an initial installation of three 90,000-kilowatt units to be installed initially with provision for three additional units, an ultimate total of six units. Spillway dam is 610 feet long, and overflow crest at elevation 391 mean sea level is surmounted by 10 radial gates, 50 feet wide by 52.9 feet high, which will provide capacity to pass a spillway design flood of 850,000 cubic feet per second. The deck will be at elevation 453 mean sea level and provides a service road and track for a gantry crane. Navigation lock is a single lift type and has clear plan dimensions of 86 by 675 feet. A navigation channel with a width of 250 feet and minimum depth of 15 feet will be provided from the mouth to mile 9.7 on Snake River.

The estimate of cost for new work (July 1963) is $124,677,200. Construction of additional recreational facilities for completed project is estimated to cost $285,000, raising total project cost to $124,962,200. Average annual maintenance cost for past 2 years was $314,466. Existing project was authorized by the River and Harbor Act approved March 2, 1945 (See H. Doc. 704, 75th Cong., 3d sess.).

Operations and results during fiscal year. Contract work for completion of powerhouse structure and installation of equipment was completed. During load rejection tests on January 4, 1962, turbine blade linkage mechanism in unit No. 1 failed. Failure resulted in extensive damage to turbine. Unit was restored to service in February 1963. Remaining work under north shore construction contract was completed. Miscellaneous contracts were completed for log boom and cable anchorages of reservoir debris disposal facilities, log conveyor portion of these facilities, and reservoir recreation facilities. A contract was awarded for repairs to spillway bays 1 and 10, and a contract was awarded for cleaning stilling basin. Both contracts were completed.

Deferred construction was performed on Union Pacific Railroad, Northern Pacific Railway, and Spokane, Portland & Seattle Railway under relocation agreements still in effect. Contract plans and specifications progressed on buildings, grounds and landscaping at site; and for navigation lock fire protection equipment. Invitations for bids for repairs to spillway stilling basin were issued.

A total of 69,500 persons visited project during calendar year 1962.

Total costs during the fiscal year were $1,726,146 for new work and $480,055 for maintenance.

Condition at end of fiscal year. Project was placed on a permanent operating basis on January 1, 1962; pool was raised to normal operating elevation 440 on April 27, 1962; and navigation lock opened for normal traffic on October 5, 1962. Acquisition of land is essentially complete. Work remaining involves a contract for installing navigation lock fire protection equipment and a contract for buildings, landscaping, and grounds development. Basic recreation facilities are about half complete. The entire project is considered to be 99.5 percent complete as of June 30, 1963. Total costs were $123,471,367 for new work, and $628,932 for maintenance.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$19,133,000 $29,299,000 $26,300,000 $9,000,000 $1,165,000 $123,652,173¹
Cost
18,812,945 27,977,829 27,555,232 8,985,842 1,726,146 123,471,367¹
Maintenance
Appropriated
150,000 509,400 659,400
Cost
148,877 480,055 628,932
Other new work data:
Unobligated balance for year ending June 30, 1963
$93,129
Appropriated for year ending June 30, 1964
1,025,027
Unobligated balances available for year ending June 30, 1964
1,118,156
Estimated additional amount needed to complete project
285,000
1Excludes $82,500 contributed funds for artificial spawning channel.

6. McNARY LOCK AND DAM, COLUMBIA RIVER, OREG.

Location. On the Columbia River, 292 miles above the mouth, near Umatilla, Oreg., and 3 miles above the mouth of the Umatilla River.

Existing Project. Provides for a dam, powerplant with 14-power-unit generating installation, navigation lock, fishways, attendant buildings and grounds, levees, drains, pumping plants, incidental irrigation and modification of railroad bridges over Columbia and Snake Rivers in order to eliminate hazards to navigation. For more detailed description, see page 1990 of Annual Report for 1962. Project is considered complete except for modification of two railroad bridges. Estimated cost of project is $294 million (July 1963). Construction of additional recreation facilities for completed project is estimated to cost $400,000, raising total project cost to $294,400,000. Average annual maintenance cost for past 5 years was $1,666,105. Existing project was authorized by River and Harbor Act of March 2, 1945. (See H. Doc. 704, 75th Cong., 3d sess.)

Operations and results during fiscal year. Negotiations were reinstigated with Union Pacific Railroad Co. and Northern Pacific Railway Co. to consummate contracts relative to modification of their bridges over Columbia and Snake Rivers, respectively. Recreation facilities were improved and maintained by both Government and local interests, and studies continued for additional development of recreation areas.

A total of 1,479,500 persons visited project during calendar year 1962. During fiscal year 1963 a total of 4,430,024 megawatt hours of electrical energy were delivered to Bonneville Power Administration, the marketing agency. A total of 1,186,000 tons of freight passed through navigation lock during calendar year 1962. Total costs for fiscal year were $1,925 for new work, and $1,539,371 for maintenance.

Condition at end of fiscal year. Negotiations are continuing with Port of Pasco for disposal to them of 11-B levee and pumping plant. Construction of existing project was begun May 5, 1947. Initial construction is essentially complete as of June 30, 1961; however addition of modifications to two railroad bridges over Columbia and Snake Rivers has decreased the percentage complete to 97. Project was placed on a permanent operation basis December 1, 1953, and pool raised to normal operating elevation 340 on December 6, 1953. Except for routine maintenance, all 14 power units were in commercial operation since February 1953. Total costs have been $285,933,358 for new work and $13,962,792 for maintenance.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$500,000 $1,144,000 $12,500 $9,176 $11,000 $286,141,676¹ ²
Cost
638,759 674,504 403,239 20,297 1,925 286,933,358¹ ²
Maintenance
Appropriated
1,645,700 1,657,770 1,810,700 1,710,000 1,602,500 14,104,170
Cost
1,643,934 1,652,116 1,794,657 1,700,449 1,539,371 13,962,792
Other new work data:
Unobligated balance for year ending June 30, 1963
$206,318
Appropriated for year ending June 30, 1964
50,000
Unobligated balances available for succeeding fiscal year ending June 30, 1964
258,318
Estimated additional amount needed to be appropriated for completion of existing project
8,208,324
¹Includes $185,000 donated funds.
²Includes $57,676 allotted under Code 710, recreation facilities on completed projects.
³Includes $46,886 allotted under Code 710, recreation facilities on completed project.

7. JOHN DAY LOCK AND DAM, COLUMBIA RIVER, WASH. AND OREG.

Location. Site is on Columbia River, about 3 miles downstream from the mouth of John Day River and about 215 miles above the mouth of Columbia River.

Existing Project. As modified consists of a dam, powerplant, navigation lock, fish ladder, and appurtenant facilities with a slackwater pool of about 75 miles long extending to McNary lock and dam. Included is relocation of railroads, highways, utilities, and communities affected by proposed reservoir. Project provides 500,000 acre-feet of flood control storage between minimum pool elevation of 257 and a maximum elevation of 268. Powerhouse provides for 20 generating units of 135,000 kilowatts each. Initial installation consists of 10 units for a total of 1,350,000 kilowatts. Estimated cost of new work, revised in 1963, is $423 million. A detailed description of project as authorized and modified appears on pages 1992 and 1993 of Annual Report for 1962.

Operations and results during fiscal year. Relocation of highways and railroads in reservoir area progressed. During the year 11 contracts were awarded for grading of 38 miles of railroad and 24 miles of highway, and for construction of a railroad bridge, a highway bridge, and two interchange structures. In addition, one 7-mile section of previously subgraded highway was paved. Preparation of plans and specifications for relocations of railroads and highways continued.

For relocation of city of Arlington, initial fill and flood channel in area were completed. Modifications and additions to water and sewer systems in Arlington were essentially complete. Construction of relocated city hall was initiated. Preparation of plans and specifications for relocation of communities continued.

At damsite, work on north shore including lock, spillway, and fish ladder was essentially complete. First phase of second-step cofferdam was completed. Plans and specifications for construction of powerhouse, south shore fish ladder, remaining sections of nonoverflow dam, raising low spillway bays, raising upstream sill in lock, and such other work as necessary to complete dam structure were advertised. Preparation of plans and specifications for electric power generators and associated electrical facilities continued.

Total costs for fiscal year were $40,323,785, all for new work.

Condition at end of fiscal year. At end of fiscal year 44 miles of railroad grading and bridge work out of 140 miles to be relocated had been placed under contract. Overall railroad work is about 5 percent complete. Thirty-nine miles of highway were placed under contract to date, of which 7.5 miles were surfaced and ready for traffic, 3 miles are ready for surfacing. Overall highway relocation work is approximately 20 percent complete. Initial fill for city of Arlington has been completed and area is being turned over to city for development. Replacement building for city hall, fire station, and library is about 70 percent complete. Work on Arlington sewer and water systems being accomplished under contract to the city is 75 percent complete. Contract for construction of navigation lock, north shore fish ladder, dam spillway and embankment is 99 percent complete.

Construction of the project started in June 1958, and the entire project is 27 percent complete. Total costs were $114,042,224, all for new work.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$7,554,000 $14,335,000 $30,900,000 $20,400,000 $39,010,000 $115,140,000
Cost
7,092,655 14,718,821 28,743,044 20,378,953 40,323,785 114,042,224
Other new work data:
Unobligated balance, June 30, 1963
$230,896
Appropriated for succeeding fiscal year ending June 30, 1964
57,000,000
Unobligated balances available for succeeding fiscal year ending June 30, 1964
57,230,896
Estimated additional amount needed to be appropriated for completion of existing project
250,860,000

8. COLUMBIA RIVER AND TRIBUTARIES ABOVE CELILO FALLS TO KENNEWICK, WASH.

Location. Project includes improvement of 128 miles of the Columbia River between the head of Celilo Falls and Kennewick, Wash. (See U.S. Geological Survey Map of Washington.)

Previous Project. Original project was adopted by the River and Harbor Act of June 10, 1872, and modified by River and Harbor Act of March 2, 1907. For further details, see page 1992 of Annual Report for 1915; page 1889, Annual Report for 1931; and page 1845, Annual Report for 1938.

Existing Project. Provides for a channel 7 feet deep and 150 feet wide at low water from Celilo Falls to Wallula, with no specified depth or width between Wallula and mouth of Snake River and for an approach channel 6 feet deep at low water from the navigation channel in Columbia River to site of port development at Arlington, Oreg.

Actual cost for new work exclusive of amounts expended on previous project was $1,356,584. Average annual maintenance cost for past 5 years was $13,112.

Incomplete channel rectification work at Owyhee Rapids, Squally Hook, and Indian Rapids, is classified as inactive and excluded from foregoing cost estimate. Cost of this portion, revised in 1954, is estimated to be $419,000.

Construction of The Dalles Dam and raising reservoir has provided a slackwater pool extending upriver to site of John Day Dam and provided slackwater over lower 25 miles of original project. Creation of pool behind McNary Dam (river mile 292) provided slackwater over upper 36 miles of original project. Remaining reach of river included in this project is comprised of approximately 67 miles of open river between The Dalles Pool and McNary Dam. Upon creation of pool behind John Day Dam, slackwater will also be provided over this reach of river, and project will be obviated.

The existing project was authorized by the following:

Acts Work authorized Documents¹
Apr. 8, 1935 Emergency Relief Appropriation Act authorized the existing project as an Emergency Relief project. Rivers and Harbors Committee Doc. 16, 63d Cong., 2d sess.
Aug. 30, 1935 Adopted existing project as a river and harbor project. Do.
Mar. 2, 1945 Arlington approach channel S. Doc. 28, 76th Cong., 1st sess.
Mar. 2, 1945 Kennewick approach channel H. Doc. 324, 77th Cong., 1st sess.²
1Contains latest published map.
2Construction of McNary Dam has obviated the necessity for this work.

Local cooperation. River and Harbor Act approved March 2, 1945, provides that for Arlington Channel, local interests give assurances that they will construct a suitable freight terminal, open to all on equal terms. These assurances were approved December 29, 1947, but a freight terminal will not be constructed because backwater of John Day Dam will inundate present terminal area.

Terminal facilities. On Columbia River from Celilo to McNary lock and dam there are five privately owned grain and oil terminals with connections to truck and rail. Facilities are adequate for existing commerce. Above McNary lock and dam are five publicly owned terminals which handle general cargo and are open for public use. These terminals are adequate for existing commerce, and general development is keeping pace with increasing demands. In addition, there are 15 privately owned terminals serving grain, petroleum, and chemical industries. Also there are five commercial marinas.

Operations and results during fiscal year. On Columbia River, soundings of navigation channel from McNary Dam to John Day Damsite indicated need for dredging at five locations. This dredging was accomplished at all five locations. Total maintenance cost including condition surveys was $29,471.

Condition at end of fiscal year. Authorized 7-foot channel, 150 feet wide has been completed to McNary lock and dam. Controlling depth of 7 feet between the head of The Dalles Pool and McNary Dam was restored by dredging in fiscal year 1962. For that portion of project within McNary pool and The Dalles pool, depths are in excess of 7 feet with minimum depth of 15 feet over upper lock sills. Arlington approach channel was completed in 1948. Total costs were $1,356,584 for new work (includes $400,000 emergency relief administration funds) and $1,040,234 for maintenance.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$1,851,195¹
Cost
1,851,195¹
Maintenance
Appropriated
$4,700 $4,950 $5,100 $33,641 $28,982 1,040,234²
Cost
4,502 5,047 5,148 33,152 29,471 1,040,234²
1Includes $494,611 for new work on previous projects. Excludes $25,000 contributed funds expended for new work.
²Includes $100,830 for maintenance from previous projects

9. OTHER AUTHORIZED NAVIGATION PROJECTS

Name of project For last full Report see Annual Report for— Cost to June 30, 1963 Estimated amount required to Complete Cost estimate (last date of revision)
Construction
Asotin Dam, Snake River, Idaho and Wash. $86,500,000 $86,500,000 (1963)
Umatilla Harbor 1952 678,000¹ 678,000 (1957)¹
1Inactive. No funds appropriated for work.

10. COLUMBIA RIVER BASIN, LOCAL FLOOD-PROTECTION PROECTS

Location. Improvements included in this project are located along the Columbia River and its tributaries.

Existing Project. Flood Control Act approved May 17, 1950, approved a general comprehensive plan for Columbia River Basin for flood control and other purposes as set forth in House Document 531, 81st Congress, 2d session, and authorized $75 million to be appropriated for the partial accomplishment of certain projects. Of this authorization, an amount not to exceed $15 million was authorized for construction of local flood protection works throughout Columbia River Basin, subject to the conditions that all work undertaken pursuant to this authority shall be economically justified prior to construction, and local cooperation specified in the 1936 Flood Control Act, as amended, shall be required. Protection to the following areas, located in the Walla Walla district, is being considered under latter authorization:

Project Federal Cost Status June 30, 1963
Appropriated Cost
Blackfoot Area, Snake River, Idaho¹ $42,796 $42,796 $42,796
Blackfoot River, Idaho² 396,100 396,074 113,883
Boise Valley, Idaho (Ada County unit)² 504,000 54,800 48,185
Camas Creek, Idaho (feasibility doubtful) 9,680 9,680
Grande Ronde Valley, Oregon¹ 8,639,000 102,458 102,458
Heise-Roberts Extension, Idaho $1,830,000 25,377 20,377
John Day River Area, Oregon² 475,000 65,572 48,172
Kendrick, Potlatch River, Idaho¹ 59,941 59,641 59,641
Little Wood River, Idaho (Carey)¹ 64,000 21,334 21,334
Lower Walla Walla River, Washington (not feasible) 4,000 4,000
Malheur River, Oregon (Vale Unit)¹ 338,580 338,580 338,580
Mill Creek, Washington (not feasible)   3,537 3,537
Mud Lake Area, Idaho (not feasible) 5,996 5,996
Palouse River, Washington 735,400
Payette Valley, Idaho³ 23,178 23,178
Portneuf River and Marsh Creek, Idaho² 748,000 81,276 81,276
Shelley Area, Snake River, Idaho¹ 32,335 32,335 32,335
South Fork Clearwater River, Idaho4 3,899 3,899
Teton River, Idaho (not feasible) $10,387 $10,387
Touchet River, Washington (not feasible) 11,198 11,198
Umatilla River, Oregon (Echo)¹ 879,000 24,145 24,145
Weiser River, Idaho¹ 550,000 88,427 88,427
Whitebird Creek, Idaho³ 1,896 1,896
Total 1,406,286 1,089,837
1Reported under "Other Authorized Flood Control Projects."
2Economic justification of work proposed has been established in compliance with conditions set forth in Flood Control Act of 1950. Reported in an individual report.
3Deferred for restudy.
4Construction of emergency work at this location has obviated the need for improvements.
Note: This list does not include improvements in Portland and Seattle Districts.

Local Cooperation. Section 3 of the Flood Control Act approved June 22, 1936, as amended, applies to all the flood-control projects.

Operations and results during fiscal year. Costs were incurred on following projects which are reported in individual reports: Blackfoot River, Snake River, Idaho; Boise Valley, Idaho; John Day River area, Oreg.; and Portneuf River and Marsh Creek, Idaho.

Condition at end of fiscal year. Following projects are reported in individual reports: Blackfoot River, Snake River, Idaho; Boise Valley, Idaho; John Day River area, Oreg.; and Portneuf River and Marsh Creek, Idaho.

A justification report on Heise-Roberts extension, Idaho, previously submitted to North Pacific Division was returned by them with recommended revisions, and subsequently approved for construction by Chief of Engineers.

Due to lack of funds, no work has been accomplished on Palouse River, Wash., since time project was conditionally authorized.

Total costs to date for all Columbia River Basin local flood protection projects in the foregoing table, including those listed under other authorized flood control projects, were $1,089,837.

Cost and Financial Summary
Fiscal year 1959 1960 1961 1962 1963 Total to
June 30, 1963¹
New Work
Appropriated
$2,969 —$5,636 $4,500 $5,000 $98,546
Cost
20,653 10,005 4,990 93,546
Other new work data:
Unobligated balance, fiscal year ending June 30, 1963
$5,000
Unobligated balances available for succeeding fiscal year ending June 30, 1964
5,000
1Comprises following projects: Camas Creek, Idaho; Heise-Roberts Extension, Idaho; Lower Walla Walla River, Wash.; Mill Creek, Wash.; Mud Lake area, Idaho; Palouse River, Wash; Payette Valley, Idaho; South Fork, Clearwater River, Idaho; Teton River, Idaho; Touchet River, Wash.; and Whitebird Creek, Idaho.

Excludes projects reported under "Other Authorized Flood Control Projects:" Blackfoot Area, Snake River, Idaho; Grande Ronde Valley, Oreg.; Kendrick, Potlatch River, Idaho; Little Wood River (Carey), Idaho; Malheur River (Vale), Oreg.; Shelley Area, Snake River, Idaho; Umatilla River (Echo), Oreg.; and Weiser River, Idaho.

Excludes projects reported in detail in an individual report: Blackfoot River, Idaho; Boise Valley, Idaho; John Day River area, Oregon; and Portneuf River and Marsh Creek, Idaho. Excludes amounts for improvements in Portland and Seattle Districts.

11. JACKSON HOLE, SNAKE RIVER, WYO.

Location. On both banks of the Snake River in the vicinity of Wilson, Wyo.

Existing Project. Plan of improvement provides for a levee with full riprap protection on right bank, extending from J.Y. Ranch, which is 10 miles upstream from the Jackson-Wilson Highway Bridge to a point 3.5 miles below same bridge—a total length of 13.5 miles. The plan also provides for a levee with full riprap protection along left bank, extending from north line of the Lucas Ranch, which is 10 miles upstream from Jackson-Wilson Highway Bridge to a point 5 miles downstream and extending 1.5 miles immediately upstream from Jackson-Wilson Highway Bridge to a point 3.5 miles below bridge for a total length of 10 miles. Existing project was authorized by the Flood Control Act approved May 17, 1950 (Public Law 516, 81st Cong., 2d sess.). The estimated cost, revised in 1963, is $2,268,000 for construction. Costs of rights-of-way are to be paid by local interests.

Local cooperation. Section 3 of the Flood Control Act approved June 22, 1936, as amended, applies. Formal assurance of local cooperation by sponsor has been accepted.

Operations and results during fiscal year. Preparation of plans and specifications for portion of project 3.5 miles below Jackson-Wilson Bridge was completed, and a construction contract awarded. Total costs during fiscal year were $14,366, all for new work.

Condition at end of fiscal year. Construction of project was initiated in November, 1957. Contracts for construction of levees and relocation of irrigation headgates upstream from Jackson-Wilson Highway Bridge are complete. With respect to the 3.5 miles below Jackson-Wilson Highway Bridge, plans and specifications for both banks are complete. The entire project is 70 percent complete. Total costs were $1,576,693, all for new work.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$320,000 $665,000 $50,000 $20,000 $1,609,000
Cost
276,960 708,937 $3,703 27,872 14,366 1,576,693
Other new work data:
Unobligated balance for year ending June 30, 1963
$12,307
Appropriated for year ending June 30, 1964
650,000
Unobligated balances available for year ending June 30, 1964
671,307

12. RIRIE RESERVOIR, WILLOW CREEK, IDAHO

Location. On Willow Creek, a tributary of Snake River, in Bonneville County, Idaho. Proposed channel improvement, which is about 1 mile north of city of Idaho Falls, Idaho, extends from junction of Sand and Willow Creeks to Snake River, see U.S. Geological Survey quadrangle map, Ucon., Idaho. Proposed dam is about one-half mile below confluence of Willow and Meadow Creeks and about 15 miles southeast of city of Idaho Falls, Idaho, see U.S. Geological Survey quadrangle map, Poplar, Idaho.

Existing Project. Proposed project includes a rockfill dam, outlet works, spillway, and some downstream channel construction. Rockfill dam is 230 feet high and 580 feet long at crest, with a total storage capacity of 135,000 acre-feet, of which 125,000 acre-feet will be usable. Concrete spillway is in ridge forming right abutment and provides capacity to pass a design flood of 13,000 cubic feet per second. Controlled outlet consists of an 8-foot concrete and steel-lined tunnel through right abutment with a hydraulic capacity of 1,000 cubic feet per second at minimum pool and 2,000 cubic feet per second at maximum pool. Channel construction below diversion to Sand Creek provides adequate channel capacity for necessary flood control releases. Improvement provides for flood control, irrigation, municipal water supply, and recreation.

Estimated cost for new work is $7,400,000 (July 1963). Existing project was authorized by Flood Control Act of 1962. (See H. Doc. 562, 87th Cong., 2d sess.)

Operations and results during fiscal year. Hydrologic studies leading to establishment of a standard project flood and maximum probable flood determination and project water supply have been started. These studies will be published as design memorandum No. 1. Design memorandum No. 2, project scoping, site selection, type of dam, and downstream channel, has been started. Initial surveys and office studies on downstream channel have been initiated. Geologic reconnaissance and foundation explorations were commenced. Coordination activities with Fish and Wildlife Service, Public Health Service, and Bureau of Reclamation were also initiated. Total costs during fiscal year were $62,964.

Condition at end of fiscal year. Design memorandum No. 1 was approximately 25 percent complete and design memorandum No. 2 approximately 35 percent complete. No construction has been done. Total costs were $62,964.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$75,000 $75,000
Cost
62,964 62,964
Other new work data:
Unobligated balance for year ending June 30, 1963
11,556
Appropriated for year ending June 30, 1964
375,000
Unobligated balances available for year ending June 30, 1964
386,556
Estimated additional amount needed to be appropriated for completion of existing project
6,950,000

13. BLACKFOOT RIVER, COLUMBIA RIVER BASIN, IDAHO

Location. Project provides flood protection to lower 16 miles of Blackfoot River along eastern boundary of Fort Hall Indian Reservation near city of Blackfoot in Bingham County, Idaho.

Existing project. Provides for widening, deepening, and shortening river channel and erection of levees through a 5-mile reach of river from river mile 10.8 to 16. It also provides for a floodwater diversion channel at river mile 10.8 to Snake River in order to protect lower 11 miles of Blackfoot River valley lands.

Existing project was conditionally authorized under section 204, Flood Control Act of May 17, 1950, subject to economic justification. Economic justification was established in fiscal year 1958. Estimated cost, revised in 1962, is $396,100 for construction.

Local cooperation. Fully complied with.

Operations and results during fiscal year. Negotiations were completed with local interests to obtain sponsorship requirements. Preparation of plans and specifications was completed. Total costs were $14,196, all for new work.

Condition at end of fiscal year. Plans and specifications are complete. No construction has been done. Total costs were $113,883, all for new work.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$42,191 $12,000 $16,083 $20,000 $295,800 $396,074
Cost
22,956 2,558 34,161 30,018 14,196 113,883
Other new work data:
Unobligated balance, June 30, 1963
$40,386
Unobligated balances available for succeeding fiscal year ending June 30, 1964
40,386

14. PORTNEUF RIVER AND MARSH CREEK, COLUMBIA RIVER BASIN, IDAHO

Location. Project is at three areas along Portneuf River and along entire length of its main tributary, Marsh Creek, all in southeastern Idaho.

Existing Project. Plan of improvement provides for channel straightening and improvement, removal of obstructions, and construction of new levees and revetments or improvements to existing levees in Blackrock area, in and adjacent to city of Pocatello and in vicinity of Inkom, all on Portneuf River. Plan also provides for channel improvement along lower 39 miles of Marsh Creek.

Existing project was authorized under Columbia River Basin plan by Flood Control Act of May 17, 1950, subject to economic justification. Justification for Pocatello unit was established in fiscal year 1953. After plans and specifications were 88 percent complete, Pocatello unit was classified inactive in 1961 due to failure of local interests to meet sponsorship requirements. After heavy floods in 1962 and 1963, interest in this unit revived, and city and county officials requested that it be reclassified from inactive category. Local interests in Inkom-Marsh Creek area have expressed little desire to participate in plan of improvement, and economic justification has not been established. Estimated cost (1960 base) of Pocatello unit is $748,000. Inkom-Marsh Creek portion of project is considered inactive and excluded from foregoing estimate. Cost of this portion, last revised in 1958, was estimated to be $617,000.

Local cooperation. Section 3, Flood Control Act of June 22, 1936, as amended, applies. In March 1963, city of Pocatello passed a $190,500 bond issue to provide funds for local cooperation requirement and requested reactivation of project.

Operations and results during fiscal year. General design memorandum was initiated for Pocatello unit. Total costs for fiscal year were $2,757.

Condition at end of fiscal year. Because 1962 and 1963 flood flows were greater than flow designed for originally in Pocatello unit, planning studies were initiated to consider providing a channel with a greater design flow. General design memorandum is 5 percent complete. No further work is proposed at this time on Inkom-Marsh Creek unit. No construction work has been done. Total costs were $76,033.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$8,000 $31,276
Cost
2,757 76,033
Other new work data:
Unobligated balance for year ending June 30, 1963
$5,243
Appropriated for year ending June 30, 1964
54,000
Unobligated balances available for year ending June 30, 1964
59,243
Estimated additional amount needed to be appropriated for completion of existing project
612,724

15. LUCKY PEAK RESERVOIR, BOISE RIVER, IDAHO

Location. On Boise River in southwestern Idaho approximately 9 miles southeast of city of Boise, and approximately 12 miles downstream from Arrowrock Reservoir.

Existing Project. Plan of improvement provides for a rolled earth-fill dam approximately 250 feet high and 1,700 feet long at crest, with a reservoir providing a total storage at normal pool level of 306,000 acre-feet. For further details see page 2000 of Annual Report for 1962. Cost of completed project was $19,081,250. Construction of additional recreation facilities for completed project is estimated to cost $363,000, raising the total project estimate to $19,444,250. Average annual maintenance cost for past 5 years was $77,678. Project was authorized by Flood Control Act of July 24, 1946.

Local Cooperation. None required.

Operations and results during fiscal year. Preparation of plans and specifications for construction of sanitary facilities, water supply system, roads, parking areas, and picnicking facilities continued. Extension of a boat launching ramp and improvement of picnic facilities was accomplished by Government forces. A well drilling contract was awarded and essentially complete. Other facilities were improved and expanded by local interests. Recreational facilities continue to show heavy usage. During calendar year 1962, 551,000 persons visited the project.

Normal operation and maintenance of project continued all year. Total costs for fiscal year were $29,429 for new work and $74,112 for maintenance.

Condition at end of fiscal year. Construction of the existing project was initiated in November 1947 and completed in June 1961. Total costs have been $19,081,250 for new work and $599,416 for maintenance.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$288,500 $37,750 $15,300 $36,000 $19,152,550¹
Cost
384,197 $55,639 111,298 10,881 29,429 19,140,392²
Maintenance
Appropriated
73,400 72,800 77,480 91,500 95,500 622,040
Cost
72,726 73,669 77,416 90,465 74,112 599,416
Other new work data:
Unobligated balance for year ending June 30, 1963
$12,068
Appropriated for year ending June 30, 1964
50,000
Unobligated balance available for year ending June 30, 1964
62,068
Estimated additional amount needed to complete project
241,700
¹Includes $71,300 allotted under Code 710, recreation facilities on completed projects.
²Includes $59,142 expended under Code 710, recreation facilities on completed projects.

16. BOISE VALLEY, COLUMBIA RIVER BASIN, IDAHO

Location. Proposed project is on Boise River in intermittent reaches of channel from vicinity of Boise, Idaho, river mile 52, downstream to the Snake River, river mile 0.

Existing Project. Previous emergency flood-control projects have been accomplished at various locations on this portion of the river. Plan of improvement provides for raising existing levees and structures to existing hydraulic design criteria. It also provides for construction of levees in reaches where protection does not presently exist.

Project was conditionally authorized under the Columbia River Basin plan by section 204 of the Flood Control Act, approved May 17, 1950, (Public Law 516, 81st Congress, 2d session), subject to economic justification. Economic justification was established in fiscal year 1962.

That portion of project in Canyon County from river mile 1 to river mile 37 has been placed in an inactive status due to inability of local interests to meet sponsorship requirements.

Estimated cost of the project (1962) is $504,000. Inactive Canyon County portion of the project is excluded from foregoing cost estimate. Cost of this inactive portion, last revised in 1962, was estimated to be $652,800.

Local Cooperation. . Section 3,Flood Control Act approved June 22, 1936, as amended, applies. Officials of Ada County have furnished a letter of intent to sponsor portion of project in Ada County. Canyon County officials have given written notice that they are unable to meet sponsorship requirements for their portion of the project.

Operations and results during fiscal year. A negotiated contract was awarded to an architectural engineering firm for preparation of general design memorandum for that portion of project in Ada County, and engineering services proceeded. Total costs for fiscal year were $29,380, all for new work.

Condition at end of fiscal year. General design memorandum is complete and has been submitted to higher authority for approval. Canyon County portion of project is in an inactive status. No construction has been done. Total costs were $48,185, all for new work.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$24,000 $39,800 —$40,000 $21,000 $54,800
Cost
1,583 3,244 $2,233 3,061 29,380 48,185
Other new work data:
Unobligated balance for year ending June 30, 1963
$6,615
Appropriated for year ending June 30, 1964
449,200
Unobligated balance available for year ending June 30, 1964
455,815

17. BRUCES EDDY RESERVOIR, NORTH FORK CLEARWATER RIVER, IDAHO

Location. Bruces Eddy Dam site is on North Fork of Clearwater River 1.9 miles above its junction with Clearwater River, near Orofino, Idaho, and about 35 miles east of Lewiston, Idaho.

Existing Project. Project as authorized to provide a straight concrete gravity dam 630 feet in effective height at normal pool elevation 1,600 and about 3,200 feet long at crest. Dam will create a reservoir having a gross storage capacity of 3,453,000 acre-feet of which 2 million acre-feet would be effective for both local and regional flood control, and for at-site and downstream power generation. In addition, reservoir pool, extending 53 miles into a rugged and relatively inaccessible timberland, will provide important transportation savings in connection with movements of marketable logs and will also afford substantial recreational benefits.

Powerhouse will provide three 100,000-kilowatt generating units to be installed initially, with provisions for three additional 100,000-kilowatt units for an ultimate installed capacity of 600,000 kilowatts.

No significant runs of salmon occur in Clearwater River; however, considerable migrations of steelhead trout are recorded at Washington Water Power Company Dam at Lewiston, Idaho, near mouth of Clearwater River. Accordingly, fish passage facilities will be provided at Bruces Eddy Dam to accommodate present fish movements and improve existing runs.

Bruces Eddy Reservoir site is also the habitat for elk, deer, and other wildlife. Project plans propose acquisition of land outside reservoir limits to mitigate losses of browse areas inundated by reservoir.

Estimated cost for new work, last revised in 1963, is $211 million for a concrete gravity dam with normal pool elevation 1,600. Planning was authorized by Flood Control Act of July 3, 1958 in accordance with plan presented in Senate Document 51, 84th Congress, 1st Session. Project is authorized for construction by Public Law 87-874, October 23, 1962. Initial appropriation for construction was by Public Works Appropriation Act of 1962.

Operations and results during fiscal year. Design memorandum No. 3, general design memorandum was submitted September 18, 1961, and approved May 22, 1962. Supplement No. 1 to design memorandum No. 3 was submitted October 24, 1962, and approved by Chief of Engineers for a straight gravity dam at upper site. Design memorandum No. 7, initial relocations access and detour road, was submitted January 8 and approved March 7, 1963. Design memorandum No. 8, part I real estate, damsite and construction area, access road related borrow and spoil areas and partial flowage and public use areas, was submitted January 7 and approved February 12, 1963. Design memorandum No. 10A, preliminary master plan, was submitted April 19, 1963, and approval is pending. Acquisition of lands for access road and related borrow is complete and damsite and construction areas are in process. Construction was initiated on access road and relocation of county road in April, 1963, and is on schedule. Surveys and explorations continued all year. Work has progressed on design memoranda for: Supplements on power installation, fish passage, and log transport; dam stress analysis; relocations of District County roads, phases II and III; diversion tunnel design, real estate design memorandum, part II; temporary field facilities; and spillway and outlet structure. Work started on hydraulic model.

Total costs during the fiscal year were $1,936,218, all for new work..

Condition at end of fiscal year. General design memorandum No. 3 and supplement No. 1 thereto have been approved. Construction on project started. Work is progressing on items above and estimated overall status of completion is 2 percent. Total costs were $4,183,519, all for new work.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$630,000 $741,000 $600,000 $700,000 $1,920,000 $4,461,000
Cost
570,956 662,978 557,167 586,199 1,936,218 4,183,519
Other new work data:
Unobligated balance for year ending June 30, 1963
$116,431
Appropriated for year ending June 30, 1964
5,400,000
Unobligated balances available for year ending June 30, 1964
5,516,431
Estimated additional amount needed to be appropriated for completion of existing project
201,139,000

18. PULLMAN, PALOUSE RIVER, WASH.

Location. On South Fork Palouse River and Missouri Flat Creek at Pullman, in eastern Washington.

Existing Project. Plan of improvement provides for flood control at Pullman, Wash., by channel rectification and intermittent levee construction along 1.36 miles of South Fork Palouse River and 0.42 mile of Missouri Flat Creek. Latest (1963) approved estimate of cost for new construction work is $2,240,000. Cost of lands and damages is to be paid by local interests.

Existing project was authorized by Flood Control Act of December 22, 1944 (H. Doc. 888, 77th Cong., 2d Sess.).

Local cooperation. In addition to usual requirements, local interests must make street, railroad and bridge modifications necessary for construction of project. Formal assurances of local cooperation were received.

Operations and results during fiscal year. A letter report to present a revised, up-to-date, economic analysis of project was initiated and essentially complete. Total costs for fiscal year were $22,067, all for new work.

Condition at end of fiscal year. Letter report is nearly complete and its submission to higher authority in first quarter of fiscal year 1964 is contemplated. No construction work has been done. Total costs were $71,334, all for new work.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$25,000 $74,267
Cost
22,067 71,334
Other new work data:
Unobligated balance for year ending June 30, 1963
$2,933
Appropriated for year ending June 30, 1964
80,000
Unobligated balances available for year ending June 30, 1964
82,933
Estimated additional amount needed to be appropriated for completion of existing project
2,085,733

19. COLFAX, PALOUSE RIVER, WASHINGTON

Location. On the Palouse River and south fork of Palouse River at and adjacent to their confluence and on Spring Flat Creek in eastern Washington.

Existing Project. Provides for flood control works in the vicinity of and through Colfax, Wash., by channel enlargement and modification, levees, floodwalls, revetments, and modification of railroad bridges. Estimated Federal cost, revised in 1963 is $4,480,000 for construction. Cost of lands and damages is to be paid by local interests.

Existing project was authorized by Flood Control Act of December 22, 1944 (H. Doc. 888, 77th Cong., 2d sess.).

Local Cooperation. Section 3, Flood Control Act of June 22, 1936, as amended, applies. In addition, local interests must make necessary street and bridge modifications, contribute $2,260 to defray cost of strengthening channel walls where necessary to support street bridges and contribute approximately $35,000 to cover cost of that portion of a railway shoofly required to pass wall construction area. Formal assurance resolution from city of Colfax has been accepted. Sponsor has acquired 90 percent of right-of-way.

Operation and results during fiscal year. First unit: Contract construction work on Palouse River continued. Second unit: Preparation of plans and specifications for work on South Fork Palouse River and Spring Flat Creek continued. Total costs for fiscal year were $1,362,723.

Condition at end of fiscal year. First Unit: Construction was started in January 1962 and is 80 percent complete. Second Unit: Design work for plans and specifications is complete. Total costs for entire project were $1,867,742.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$28,300 $320,556 $350,000 $1,100,000 $2,055,707
Cost
$51,849 88,524 100,359 130,589 1,362,723 1,867,742
Other new work data:
Unobligated balance, fiscal year ending June 30, 1963
$21,332
Appropriated for year ending June 30, 1964
600,000
Unobligated balances available for year ending June 30, 1964
621,332
Estimated additional amount needed to be appropriated for completion of existing project
1,824,293

20. DAYTON, TOUCHET RIVER, WASHINGTON

Location. On both banks of Touchet River, through city of Dayton, 25 miles northeast of Walla Walla, Wash.

Existing Project. Plan of improvement provides for construction of earth and gravel levees and enlargement and straightening channel through city of Dayton, Wash. Project will provide protection for city of Dayton against floods with a discharge more than 1.5 times as great as that of the maximum flood of record which occurred in 1931. Existing project was authorized by Flood Control Act of August 18, 1941. Latest (1963) approved estimate of total Federal cost is $350,000 and $3,950 to be paid by local interests.

Local Cooperation. Section 3, Flood Control Act of June 22, 1936, as amended, applies. Assurances of local cooperation have been accepted. Sponsor has acquired 85 percent of right-of-way.

Operation and results during fiscal year. Preparation of plans and specifications continued. Total costs for fiscal year were $33,190.

Condition at end of fiscal year. Preparation of plans and specifications is approximately 80 percent complete. No construction has been done. Total costs were $77,371.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$30,377 $5,000 $32,000 $83,441
Cost
18,656 9,461 33,190 77,371
Other new work data:
Unobligated balance, fiscal year ending June 30, 1963
$6,070
Appropriated for year ending June 30, 1964
266,559
Unobligated balances available for year ending June 30, 1964
272,629

21. MILL CREEK, WASH.

Location. Near Walla Walla, Wash., on Mill Creek, a tributary of Walla Walla River.

Existing Project. Consists of an off-stream storage dam, outlet works, diversion works, division structures, and improved channel. Project was authorized by Flood Control Act of June 28, 1938. Flood Control Act approved August 18, 1941 (H. Doc. 719, 76th Cong. 3d sess.), modified project as recommended by Chief of Engineers. For further detials see page 2005 of Annual Report for 1962. Cost of completed project was $2,162,155. Construction of recreation facilities for completed project is estimated to cost $320,000, raising total project estimate to $2,392,155. Average annual maintenance cost for past 5 years was $22,692.

Local Cooperation. Portions of project required local cooperation. These requirements have been met. Ordinary operation and maintenance by local interests for calendar year 1962 cost $7,863. Total expenditures to date by local interests are $384,715. For further details see page 2006 of Annual Report for 1962.

Operations and results during fiscal year. New work: Planning continued for development and use of recreation facilities. Contract to construct a water system and sanitary facilities was completed, and damaged comfort station roof was replaced. A hired labor contract was awarded for grading roads, parking areas, and picnicking areas; and placement of top soil in general use areas.

Maintenance: Ordinary operations and maintenance by Government forces continued. Reservoir regulation was routine and diversion of water for bed sealing continued. During calendar year 1962, 41,000 persons visited project.

Total costs for the fiscal year were $42,986, for new work, and $24,710 for maintenance.

Condition at end of fiscal year. Construction of dam and appurtenant works was completed in 1942. Paving channel through city of Walla Walla was completed in 1948. For dates of minor improvements, relocations, and extraordinary maintenance see page 2006 of Annual Report for 1962. Diversion of water for bed sealing operations, initiated in 1952, is being continued. Total costs were $2,215,902 for new work, and $716,004 for maintenance. In addition, cost of new work from contributed funds was $80,000.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$33,000 $3,524 $22,000 $2,220,679¹ ²
Cost
3,047 7,713 42,986 2,215,902¹ ³
Maintenance
Appropriated
$20,100 23,470 23,020 22,000 26,800 718,270
Cost
20,341 23,484 23,073 21,854 24,710 716,004
Unobligated balance, fiscal year ending June 30, 1963
$3,573
Appropriated for year ending June 30, 1964
20,000
Unobligated balances available for succeeding fiscal year ending June 30, 1964
23,573
Estimated additional amount needed to complete project
151,476
¹In addition, $80,000 was expended for new work from contributed funds.
²Includes $58,524 allotted under Code 710, recreation facilities on completed projects.
³Includes $36,524 allotted under code 710, recreation facilities on completed projects.

22. PILOT ROCK, BIRCH CREEK, OREG.

Location. On East and West Birch Creeks, respectively, in Pilot Rock, 15 miles south of Pendleton, Oreg.

Existing Project. Plan of improvement provides for removal of gravel bars, brush, and debris from channel; elimination of abrupt turns and objectionable bends in alignment by construction of new channels; construction of levees and sloping of banks; protection of channel walls by rock revetment; and removal or reconstruction of existing irrigation headworks, bridges and other structures in path of improvement. In survey report on Umatilla River and tributaries, dated June 30, 1955, plan of improvement for Pilot Rock, Birch Creek, Oreg., was expanded to afford protection for town of Pilot Rock and industrial area on main stem of Birch Creek. Improvement proposed on West Birch Creek will begin upstream from Alder Street. Improvement on East Birch Creek will begin at a point upstream from Alder Street and extend through town to confluence of the two forks. Improvement on main stem of Birch Creek would extend from confluence of forks to a point downstream of industrial area. Existing project was authorized by Flood Control Act of August 18, 1941. Plan of improvement was revised in Umatilla River and tributaries survey report of June 30, 1955. Estimated cost, revised in 1963, is $394,000 for construction and $25,000 for lands and damages to be paid by local interests.

Local cooperation. Section 3, Flood Control Act of June 22, 1936, as amended, applies. In addition, local interests must bear cost of all relocations. City of Pilot Rock in a letter dated March 5, 1963, indicated financial inability to meet sponsorship requirements and requested project be classified deferred.

Operations and results during fiscal year. Meetings were held with city officials of Pilot Rock to determine their attitude and willingness to meet sponsorship requirements. Of a $33,000 work allowance in fiscal year 1963 for preconstruction planning of small authorized project, $30,000 was revoked because of lack of sponsorship. Total costs for fiscal year were $858, all for new work.

Condition at end of fiscal year. Authority has been requested to classify project as inactive. No further work is scheduled. Total costs were $4,558, all for new work.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$3,000 $6,700
Cost
858 4,558
Other new work data:
Unobligated balance for year ending June 30, 1963
$2,142
Unobligated balances available for year ending June 30, 1964
2,142
Estimated additional amount needed to be appropriated for completion of existing project
387,300

23. JOHN DAY RIVER, COLUMBIA RIVER BASIN, OREG.

Location. Proposed project is at intermittent locations along John Day River, Oreg., from Spray, river mile 167, to a point above John Day, near river mile 143 and along lower 12 miles of North Fork and lower 4 miles of South Fork.

Existing Project. Present investigations have shown only two reaches with required economic justification. Reach "1" begins immediately below town of Mount Vernon, river mile 233, and extends upstream fro 2 miles. Reach "2" begins about one-half mile below city of John Day, river mile 241, and extends upstream 1.5 miles through John Day and upstream 1.7 miles along Canyon Creek which converges with John Day River in city.

Project was conditionally authorized under Columbia River Basin plan by section 204, Flood Control Act of May 17, 1950, subject to economic justification. Economic justification was established in 1962.

Estimated cost of project (1963) is $475,000. This cost includes only the two reaches found to be economically feasible in 1962 justification report.

Local cooperation. Section 3, Flood Control Act of June 22, 1936, as amended, applies. Officials of Grant County furnished a letter of intent to sponsor portions of project which are in the county. City officials of John Day furnished a letter of intent for sponsorship in John Day.

Operations and results during fiscal year. Justification report was fully approved and work on a general design memorandum started. A contract for design studies was awarded to an architectural engineering firm, and firm given notice to proceed. Total costs for fiscal year were $13,923 all for new work.

Condition at end of fiscal year. Preparation of general design memorandum is 60 percent complete. No construction has been done. Total costs were $48,172, all for new work.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
New Work
Appropriated
$15,772 $17,800 $12,000 $20,000 $65,572
Cost
4,087 $6,398 22,562 1,201 13,023 48,172
Other new work data:
Unobligated balance for year ending June 30, 1963
$14,156
Appropriated for year ending June 30, 1964
25,000
Unobligated balances available for year ending June 30, 1964
39,156
Estimated additional amount needed to be appropriated for completion of existing project
384,428

24. OTHER AUTHORIZED FLOOD CONTROL PROJECTS

Name of project For last full Report see Annual Report for— Cost and expenditures to June 30, 1962
(Construction)
Estimated amount required to complete Cost estimate (last date of revision)¹
Arlington, Alkali Canyon, Oreg.² ³ 19504 $20,1125 $699,560 $723,000 (1960)
Blackfoot area, Snake River, Columbia River Basin, Idaho 1958 42,796 (6)
Blackfoot Reservoir, Blackfoot River, Idaho 870,000 870,000 (1963)
Grande Ronde Valley, Columbia River Basin, Oreg.7 1958 102,458 8,536,542 8,639,000 (1960)
Heise-Roberts area, Snake River, Idaho 1955 1,575,838 (6)
Kendrick, Potlatch River, Columbia River Basin, Idaho 1960 59,941 (6)
Lewiston-Clarkston levees8 1950
Little Wood River (Carey), Columbia River Basin, Idaho³ 1960 21,334 42,666 64,000 (1958)
Malheur Improvement Dist., Snake River, Oreg. 1957 55,894 (6)
Malheur River, Columbia River Basin, Oreg., Vale Unit 1961 341,580 (6)
Malheur River, Columbia River Basin, Oreg., Willow Creek Unit³ 1961 266,000 266,000 (1959)
Milton-Freewater, Walla Walla River, Oreg. 1956 886,956 (6)
Pendleton, Umatilla River, Oreg. (flood control works—Public Law 738, 74th Cong.) 1939 143,263 (6)
Pendleton, Umatilla River, Oreg., State Hospital and city areas (local flood protection project—Public Law 738, 74th Cong., June 22, 1936) 1960 276,848 (6)
Pendleton, Umatilla River, Oreg., Riverside area unit (local flood protection project—Public Law 516, 81st Cong., May 17, 1950)7 1960 356,000 356,000 (1956)
Shelley Area, Snake River, Columbia River Basin, Idaho 1958 32,335 (6)
Umatilla River (Echo), Columbia River Basin, Oreg.3 1960 24,145 854,855 879,000 (1959)
Weiser River, Columbia River Basin Idaho9 1960 88,427 461,573 550,000 (1963)
1Excludes any preauthorization studies costs.
2Protection to be provided in connection with John Day Lock and Dam, Columbia River, Wash. and Oreg.
3Inactive.
4Reported by Portland District prior to 1951.
5In addition, $3,328 was spent in fiscal year 1960 under authorization of Public Law 685, 84th Congress. See Annual Report for fiscal year 1960, page 1887.
6Completed.
7Deferred for restudy.
8Withdrawn as a local flood protection project, June 1959. To be included as a feature of Lower Granite lock and dam, Snake River, Idaho and Wash.)
9Awaiting local sponsorship.

25. INSPECTION OF COMPLETED FLOOD CONTROL WORKS

Upon completion of construction, projects authorized subject to specified conditions of local cooperation are transferred to responsible local interests for operation and maintenance, in accordance with requirements of authorizing legislation. Inspections are made to determine compliance of local interests with assurances given regarding operation and maintenance and physical condition of the improvements. Local interests were advised, as necessary, of measures required to maintain these projects in accordance with standards prescribed by regulations. This report includes those projects authorized by Congress, and Public Law 685.

Operations and results during fiscal year. Number of projects inspected during the fiscal year in various river basins are summarized:

River Basins Inspections
Little Wood 2
Potlatch 1
Malheur 1
Salmon 2
Snake 5
Umatilla 2
Walla Walla 3

Total costs during the fiscal year were $6,401.

Cost and Financial Summary
  Fiscal year ending June 30 Total to June 30, 1963
1959 1960 1961 1962 1963
Maintenance:
Appropriated
$10,000 $7,250 $4,000 $4,900 $6,200 $47,350
Cost
10,097 7,195 3,955 5,000 6,401 47,548

26. FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION

Small flood control projects not specifically authorized by Congress. (Sec. 205, 1948 Flood Control Act, as amended, Public Law 858, 80th Cong., June 30, 1948)

Project Location Date
authorized
Date construction Federal
cost
(actual)
Started Completed
Connell, Wash. Connell, Wash. Oct. 6, 1961 $9,791
Lower Dry Creek Tributary of Walla Walla River, Wash. July 23, 1956 September 1960 October 1961 459¹
Yakima River West Richland, Wash. Sept. 7, 1960 August 1962 189,306²
¹Final payment on Union Pacific Railroad contract.
²Excludes $9,000 expended from contributed funds.

Emergency flood-control activities—Repair, flood fighting, and rescue work. (PL 99, 84th Cong., and antecedent legislation.)

Project Location Date
authorized
Date construction Federal
cost
(actual)
Started Completed
Advance preparation Walla Walla District Continuing $10,431
1962 postflood report Southeastern Idaho Dec. 5, 1962 12,991
Flood emergency repair Teton River, Rexburg, Idaho Apr. 27, 1962 March 1963 June 1963 29,628
Flood emergency operations Southeastern Idaho Feb. 26, 1963 144
Do
Powder River, Baker, Oreg. do 1,792
Do
Palouse River, Colfax, Wash. do 1,689
Do
Clearwater River, Idaho do 724
Do
Malheur River, Oreg. do 1,027
1963 flood fight Southeastern Idaho Feb. 4, 1963 44,412
Do
Yakima, Wash. do 4,987
Do
Portneuf River, Idaho do 65
Do
Blackfoot area, Idaho do 281
Do
Weiser, Idaho do 1,719
Do
Powder River area, Idaho do 891
Do
Palouse River area, Colfax, Wash. do 999
Do
Clearwater River area, Spaulding, Idaho do 991
Do
Lava Hot Springs, Idaho do 2,603
Do
Swan Lake location, Idaho do 297
Do
Downey location, Idaho do 369
Do
Merrill location, Idaho do 312
Do
Loving location, Idaho do 203
Do
Inkom location, Idaho do 234
Do
Trip location, Idaho do 269
Do
Rowe location, Idaho do 394
Do
Newton location, Idaho do 191
Repair and restoration Heise-Roberts area, Idaho Jan. 8, 1963 May 1963 June 1963 32,611

27. SCHEDULING OF FLOOD CONTROL OPERATIONS

Coordination of functional regulation of reservoirs under section 7, Flood Control Act of 1944, was maintained for Jackson Lake, Palisades, Little Wood, Arrowrock, and Anderson Ranch Reservoirs. Similar coordination under provisions of Federal Power Commission license was maintained for Brownlee and Oxbow projects of Idaho Power Company. In coordination with Bureau of Reclamation, work continued in preparing a plan of operation for Bully Creek Reservoir in Malheur River Basin. Total costs during fiscal year were $10,134.

28. SURVEYS

Total cost of work during the fiscal year was $109,355, spent on following:

Location Cost
Navigation Studies
Snake River downstream from Weiser, Idaho $925
Flood-Control Studies
Upper Snake River above Weiser, Idaho 91,245
Mill Creek, Wash. 2,231
Willow Creek, Heppner, Oreg. 16,446
Touchet River, Wash. 6,848
Grande Ronde River, Oreg. 2,911
Walla Walla River, Wash. 18,988
Boise River, Idaho 54,073
Esquatzel Coulee, Wash. 434
Cooperatives studies—Soil Conservation Service 4,946
Cooperative studies—Bureau of Reclamation (Public Law 984-84) 3,848
Cooperative studies—Bureau of Reclamation (other authorities) 14,983
Total flood-control studies 217,878

Unexpended balance of $21,598, plus an additional sum of $218,700, can be profitably applied during fiscal year 1964 for flood control studies, $211,558, and cooperative studies with other agencies, $28,740.

29. COLLECTION AND STUDY OF BASIC DATA

Flood plain studies. Flood plain studies: A flood plain in formation study of a portion of city of Richland, Wash., was completed in accordance with a request of the city. Report on study is awaiting approval by Chief of Engineers before being released to public. Cost during fiscal year was $4,894. Unexpended balance was $870.

30. RESEARCH AND DEVELOPMENT

Hydrologic Studies. Investigations were continued to improve forecasting procedures with respect to floods and seasonal runoff volumes. Cooperation with University of Idaho continued for research and development of radio-telemetering of meteorological and hydrological data. Preliminary investigations were made of heavy rainstorms that occurred in Walla Walla District. Other general hydrologic studies continued. Total costs for fiscal year were $5,768. There was no unexpended balance.