US Army Corps of Engineers
Walla Walla District

Report of the Chief of Engineers
on Civil Works Activities
Fiscal Year 1985

Department of the Army Corps of Engineers
Extract Report of the Walla Walla District

Table 39-K
Snake River Downstream from Johnson Bar Landing, Oregon, Washington, and Idaho
(See Section 26 of Text)


Project Estimated Cost
(Corps of
Engineers
Funds Only)
New Work to
September 30, 1985
Maintenance to
September 30, 1985
Percent
Completed
Construction
Started
Approp. CostApprop. Cost
Ice Harbor Lock and Dam
Initial Project $129,578,480$129,578,480 $129,578,480$45,374,103 $45,021,475100FY 57
Code 710 Recreation Facilities914,256914,256 914,256----100 FY 57
Power Units 4-6 36,748,02136,748,02136,748,021 ----100FY 71
Totals 167,240,757 167,240,757 167,240,757 45,374,103 45,021,475 100
Little Goose Lock and Dam
Initial Project 160,413,215160,413,215160,413,215 35,509,39434,889,018100 FY 63
Power Units 4-6 60,941,80760,941,80760,941,807 ----100FY 74
Totals 221,355,022 221,355,022 221,355,022 35,509,394 34,889,018 100
Lower Granite Lock and Dam
Initial Project 321,503,981321,503,981321,503,979 36,194,29735,885,275100 FY 65
Code 710 Recreation Facilities63,80063,800 63,800---100 FY 84
Power Units 4-6 46,212,53446,212,53446,212,534 ----100FY 74
Totals 367,780,315 367,780,315 367,780,313 36,194,297 35,885,275 100
Lower Monumental Lock and Dam
Initial Project 184,712,361184,712,361184,712,361 30,747,40230,394,396100 FY 61
Power Units 4-6 51,661,37151,661,37151,661,371 ----100FY 75
Totals 236,373,732 236,373,732 236,373,732 30,747,402 30,394,396 100
Open River, Lewiston to Johnson Bar Landing
34,613 34,6131 34,6131 371,603 367,9432
Open River, Pasco to Lewiston
------ 4,3504,350
Totals Existing Projects
992,784,439 992,784,439 992,784,437 148,201,149 146,562,457 100
Previous Projects, Pasco to Lewiston
400,150400,150 400,150186,570186,570
Totals, Authorized Projects
993,184,589 993,184,589 993,184,587 148,387,719 146,749,027
1New work appropriations used for maintenance prior to 1953.
2Includes $18,723 FY 1985 project condition survey cost.

Return to the Annual Report Table of Contents