US Army Corps of Engineers
Walla Walla District

Report of the Chief of Engineers
on Civil Works Activities
Fiscal Year 1988

Department of the Army Corps of Engineers
Extract Report of the Walla Walla District

Table 39-K
Snake River Downstream from Johnson Bar Landing, Oregon, Washington, and Idaho
(See Section 22 of Text)


Project Estimated Cost
(Corps of
Engineers
Funds Only)
New Work to
September 30, 1988
Maintenance to
September 30, 1988
Percent
Completed
Construction
Started
Approp. CostApprop. Cost
Ice Harbor Lock and Dam
Initial Project $129,578,480$129,578,480 $129,578,480$61,495,674 $60,838,627100FY 57
Code 710 Recreation Facilities914,256914,256 914,25600100 FY 57
Power Units 4-6 36,748,02136,748,02136,748,021 00100FY 71
Fish Bypass Program 400,000 0000 0
Totals 167,640,757 167,240,757 167,240,757 61,495,674 60,838,627 100
Little Goose Lock and Dam
Initial Project160,413,215 160,413,215 160,413,215 49,611,60549,046,366100 FY 63
Power Units 4-6 60,941,80760,941,80760,941,807 00100FY 74
Fish Bypass Program 17,200,000 3,000,000000 0
Totals 238,555,022 224,355,022 221,355,022 49,611,605 49,046,366 100
Lower Granite Lock and Dam
Initial Project 321,503,981 321,503,981 321,503,979 62,232,30261,720,945100 FY 65
Code 710 Recreation Facilities63,80063,800 63,80000100 FY 84
Power Units 4-6 46,212,53446,212,53446,212,534 00100FY 74
Fish Bypass Program 15,500,000 5,661,00019,40500
Totals 383,280,215 373,441,315 367,799,718 62,232,302 61,720,945
Lower Monumental Lock and Dam
Initial Project 184,712,361 184,712,361 184,712,361 46,856,23245,382,977100 FY 61
Power Units 4-6 51,661,37151,661,37151,661,371 00100FY 75
Fish Bypass Program 19,400,000 20,000 000
Totals 255,773,732 236,393,732 236,373,732 46,856,232 45,382,977 100
Open River, Lewiston to Johnson Bar Landing
34,613 34,6131 34,613373,955 370,6812
Open River, Pasco to Lewiston
000 4,3504,350
Totals Existing Projects
1,045,284,339 1,001,465,439 992,803,842 220,574,118 217,363,946 100
Previous Projects, Pasco to Lewiston
400,150400,150 400,150186,570186,570
Totals, Authorized Projects
1,045,684,489 1,001,865,589 993,203,992 220,760,688 217,550,516
1New work appropriations used for maintenance prior to 1953.
2Includes $8,300 appropriated and $6,727 expended in FY 88 for project condition survey cost.