Table 39-K
Snake River Downstream from Johnson Bar Landing, Oregon, Washington, and Idaho
(See Section 23 of Text)


Project Estimated Cost
(Corps of
Engineers
Funds Only)
New Work to
September 30, 1989
Maintenance to
September 30, 1989
Percent
Completed
Construction
Started
Approp. CostApprop. Cost
Ice Harbor Lock and Dam
Initial Project $129,578,480$129,578,480 $129,578,480$68,841,979 $68,715,526100FY 57
Code 710 Recreation Facilities914,256914,256 914,25600100 FY 57
Power Units 4-6 36,748,02136,748,02136,748,021 00100FY 71
Fish Bypass Program 789,0003 690,000248,48700 31
Totals 168,029,757 167,930,757 167,489,244 68,841,979 68,715,326 99
Little Goose Lock and Dam
Initial Project160,413,215 160,413,215 160,413,215 53,316,40553,304,005100 FY 63
Power Units 4-6 60,941,80760,941,80760,941,807 00100FY 74
Fish Bypass Program 25,5000,0003 7,963,0006,391,06100 25FY 89
Totals 246,855,022 229,318,022 227,746,083 53,316,405 53,304,005 92
Lower Granite Lock and Dam
Initial Project 321,503,981 321,503,981 321,503,979 70,002,60269,898,018100 FY 65
Code 710 Recreation Facilities63,80063,800 63,80000100 FY 84
Power Units 4-6 46,212,53446,212,53446,212,534 00100FY 74
Fish Bypass Program 23,300,0003 5,098,0003,801,16000 16FY 88
Totals 391,080,315 372,878,315 371,581,473 70,002,602 69,898,018 95
Lower Monumental Lock and Dam
Initial Project 184,712,361 184,712,361 184,712,361 52,693,53252,653,104100 FY 61
Power Units 4-6 51,661,37151,661,37151,661,371 00100FY 75
Fish Bypass Program 34,300,0003 2,160,000 363,114001 FY 90
Totals 270,673,732 238,533,732 236,736,846 52,693,532 52,653,104 87
Open River, Lewiston to Johnson Bar Landing
34,613 34,6131 34,613377,578 377,5782
Open River, Pasco to Lewiston
000 4,3504,350
Totals Existing Projects
1,076,673,439 1,008,659,439 1,003,588,259 245,236,523 244,952,381 100
Previous Projects, Pasco to Lewiston
400,150400,150 400,150186,570186,570
Totals, Authorized Projects
1,077,073,589 1,009,095,589 1,003,988,409 245,423,093 245,138,951
1New work appropriations used for maintenance prior to 1953.
2Includes $3,700 appropriated and $6,897 expended in FY 89 for project condition survey cost.
3Does not include mitigation analysis.

Return to the Annual Report Table of Contents
Return to the Civil Works Activities Page