Report of the Chief of Engineers
on Civil Works Activities
Fiscal Year
1989
Department of the Army Corps of
Engineers
Extract Report of the Walla Walla
District
Table 39-K
Snake River
Downstream from Johnson Bar Landing, Oregon,
Washington, and Idaho
(See Section 23 of Text)
| Project | Estimated Cost (Corps of Engineers Funds Only) |
New Work to September 30, 1989 |
Maintenance to September 30, 1989 |
Percent Completed |
Construction Started | ||
| Approp. | Cost | Approp. | Cost | ||||
| Ice Harbor Lock and Dam | |||||||
| Initial Project | $129,578,480 | $129,578,480 | $129,578,480 | $68,841,979 | $68,715,526 | 100 | FY 57 |
| Code 710 Recreation Facilities | 914,256 | 914,256 | 914,256 | 0 | 0 | 100 | FY 57 |
| Power Units 4-6 | 36,748,021 | 36,748,021 | 36,748,021 | 0 | 0 | 100 | FY 71 |
| Fish Bypass Program | 789,0003 | 690,000 | 248,487 | 0 | 0 | 31 | |
| Totals | 168,029,757 | 167,930,757 | 167,489,244 | 68,841,979 | 68,715,326 | 99 | |
| Little Goose Lock and Dam | |||||||
| Initial Project | 160,413,215 | 160,413,215 | 160,413,215 | 53,316,405 | 53,304,005 | 100 | FY 63 |
| Power Units 4-6 | 60,941,807 | 60,941,807 | 60,941,807 | 0 | 0 | 100 | FY 74 |
| Fish Bypass Program | 25,5000,0003 | 7,963,000 | 6,391,061 | 0 | 0 | 25 | FY 89 |
| Totals | 246,855,022 | 229,318,022 | 227,746,083 | 53,316,405 | 53,304,005 | 92 | |
| Lower Granite Lock and Dam | |||||||
| Initial Project | 321,503,981 | 321,503,981 | 321,503,979 | 70,002,602 | 69,898,018 | 100 | FY 65 |
| Code 710 Recreation Facilities | 63,800 | 63,800 | 63,800 | 0 | 0 | 100 | FY 84 |
| Power Units 4-6 | 46,212,534 | 46,212,534 | 46,212,534 | 0 | 0 | 100 | FY 74 |
| Fish Bypass Program | 23,300,0003 | 5,098,000 | 3,801,160 | 0 | 0 | 16 | FY 88 |
| Totals | 391,080,315 | 372,878,315 | 371,581,473 | 70,002,602 | 69,898,018 | 95 | |
| Lower Monumental Lock and Dam | |||||||
| Initial Project | 184,712,361 | 184,712,361 | 184,712,361 | 52,693,532 | 52,653,104 | 100 | FY 61 |
| Power Units 4-6 | 51,661,371 | 51,661,371 | 51,661,371 | 0 | 0 | 100 | FY 75 |
| Fish Bypass Program | 34,300,0003 | 2,160,000 | 363,114 | 0 | 0 | 1 | FY 90 |
| Totals | 270,673,732 | 238,533,732 | 236,736,846 | 52,693,532 | 52,653,104 | 87 | |
| Open River, Lewiston to Johnson Bar Landing | |||||||
| 34,613 | 34,6131 | 34,613 | 377,578 | 377,5782 | |||
| Open River, Pasco to Lewiston | |||||||
| 0 | 0 | 0 | 4,350 | 4,350 | |||
| Totals Existing Projects | |||||||
| 1,076,673,439 | 1,008,659,439 | 1,003,588,259 | 245,236,523 | 244,952,381 | 100 | ||
| Previous Projects, Pasco to Lewiston | |||||||
| 400,150 | 400,150 | 400,150 | 186,570 | 186,570 | |||
| Totals, Authorized Projects | |||||||
| 1,077,073,589 | 1,009,095,589 | 1,003,988,409 | 245,423,093 | 245,138,951 | |||
| 1New work appropriations used for maintenance prior to 1953. 2Includes $3,700 appropriated and $6,897 expended in FY 89 for project condition survey cost. 3Does not include mitigation analysis. | |||||||