on Civil Works Activities
Fiscal Year 1991

Department of the Army Corps of Engineers
Extract Report of the Walla Walla District

Table 39-K
Snake River Downstream from Johnson Bar Landing, Oregon, Washington, and Idaho
(See Section 23 of Text)


Project Estimated Cost
(Corps of
Engineers
Funds Only)
New Work to
September 30, 1991
Maintenance to
September 30, 1991
Percent
Completed
Construction
Started
Approp. CostApprop. Cost
Ice Harbor Lock and Dam
Initial Project $129,578,480$129,578,480 $129,578,480$74,200,004 $73,885,192100FY 57
Code 710 Recreation Facilities914,256914,256 914,25600100 FY 57
Power Units 4-6 36,748,02136,748,02136,748,021 00100FY 71
Fish Bypass Program 0 789,000635,79700
Totals 167,240,757 168,029,757 167,876,554 74,200,004 73,885,192 87
Little Goose Lock and Dam
Initial Project160,413,215 160,413,215 160,413,215 57,027,72956,876,520100 FY 63
Power Units 4-6 60,941,80760,941,80760,941,807 00100FY 74
Fish Bypass Program 25,5000,0003 12,006,00011,462,99600 44FY 89
Totals 246,855,022 233,361,022 232,818,018 57,027,729 56,876,520 91
Lower Granite Lock and Dam
Initial Project 321,503,981 321,503,981 321,503,979 75,550,56875,208,098100 FY 65
Code 710 Recreation Facilities63,80063,800 63,80000100 FY 84
Power Units 4-6 46,212,53446,212,53446,212,534 00100FY 74
Fish Bypass Program 23,300,0003 7,056,0005,798,69500 24FY 88
Totals 391,080,315 374,836,315 373,579,008 75,550,568 75,208,098 93
Lower Monumental Lock and Dam
Initial Project 184,712,361 184,712,361 184,712,361 56,655,13756,413,959100 FY 61
Power Units 4-6 51,661,37151,661,37151,661,371 00100FY 75
Fish Bypass Program 34,300,0003 2,259,000 1,698,262006 FY 90
Totals 270,673,732 238,632,732 238,071,994 56,655,137 56,413,959 87
Open River, Lewiston to Johnson Bar Landing
34,613 34,6131 34,613389,019 379,6752
Open River, Pasco to Lewiston
000 4,3504,350
Totals Existing Projects
1,075,884,439 1,014,894,439 1,012,308,187 263,826,807 262,767,794 100
Previous Projects, Pasco to Lewiston
400,150400,150 400,150186,570186,570
Totals, Authorized Projects
1,076,284,589 1,015,294,589 1,012,780,337 264,013,377 262,954,364
1New work appropriations used for maintenance prior to 1953.
2Includes $11,364 appropriated and $2,097 expended in FY 90 for project condition survey cost.
3Does not include mitigation analysis.

Return to the Annual Report Table of Contents