US Army Corps of Engineers
Walla Walla District

Report of the Secretary of the Army
on Civil Works Activities for Fiscal Year 1995

Department of the Army Corps of Engineers
Extract Report of the Walla Walla District

Table 39-J
Snake River Downstream from Johnson Bar Landing, Oregon, Washington, and Idaho
(See Section 20 of Text)


ProjectEstimated Cost
(Corps of
Engineers
Funds Only)
New Work to
September 30, 1995
Maintenance to
September 30, 1995
Percent
Completed
Construction
Started
Approp.CostApprop. Cost
Ice Harbor Lock and Dam
Initial Project
Code 710 Rec Facilities
Power Units 4-6
Fish Bypass Program
$129,578,480
914,256
36,748,021
40,215,0003
$129,578,4804
914,256
36,748,021
20,517,000
$129,578,4804
914,256
36,748,021
20,517,956
$114,845,404
0
0
0
$114,639,316
0
0
0
100
100
100
53
FY 57
FY 57
FY 71
FY 91
Totals207,455,757 187,757,7574 187,758,7134 114,845,404114,639,31693
Little Goose Lock and Dam
Initial Project
Power Units 4-6
Fish Bypass Program
160,413,215
60,941,807
39,610,0003
160,413,2155
60,941,807
24,639,000
160,413,215
60,941,807
24,614,294
85,807,558
0
0
85,702,585
0
0
100
100
50
FY 63
FY 74
FY 89
Totals260,965,022 245,994,0225 245,969,3165 85,807,55885,702,58592
Lower Granite Lock and Dam
Initial Project
Code 710 Rec Facilities
Power Units 4-6
Fish Bypass Program
321,503,981
63,800
46,212,534
75,813,0003
321,503,9816
63,800
46,212,534
17,300,000
321,503,9796
63,800
46,212,534
17,066,595
110,449,468
0
0
0
110,328,532
0
0
0
100
100
100
29
FY 65
FY 84
FY 74
FY 88
Totals443,593,315 385,080,3156 384,846,9086 110,449,468110,328,53293
Lower Monumental Lock and Dam
Initial Project
Power Units 4-6
Fish Bypass Program
184,712,361
51,661,371
35,500,0003
184,712,3617
51,661,371
28,934,0009
184,712,3617
51,661,371
28,885,242
84,239,008
0
0
84,205,949
0
0
100
100
75
FY 61
FY 75
FY 90
Totals272,873,732 265,307,7327 265,258,9747 84,239,00084,205,94996
Open River, Lewiston to Johnson Bar Landing
34,61334,6131 34,613399,5192 394,318
Open River, Pasco to Lewiston
0004,3504,350
Totals Existing Projects
1,184,922,4391,084,174,439 1,083,868,524395,745,307395,275,050 94
Previous Projects, Pasco to Lewiston
400,140400,150400,150186,570186,570
Totals, Authorized Projects
1,185,322,5891,084,574,5898 1,084,268,6743395,931,877 395,461,620
1New work appropriations used for maintenance prior to 1953.
2Includes $1,000 appropriated and $1,116 expended in FY 95 for project condition survey cost.
3Does not include mitigation analysis.
4Includes $203,000 appropriated and $201,931 expended for Columbia River Fish Mitigation Program.
5Includes $370,000 appropriated and #354,589 expended for Columbia River Fish Mitigation Program.
6Includes $1,628,000 appropriated and $1,626,084 expended for Columbia River Fish Mitigation Program.
7Includes $11,132,000 appropriated and $10,949,493 expended for Columbia River Fish Mitigation Program.
8Includes $13,333,000 appropriated and $13,136,097 expended for Columbia River Fish Mitigation Program.