Report of the Secretary of the Army
on Civil Works Activities for Fiscal Year 1996

Department of the Army Corps of Engineers
Extract Report of the Walla Walla District

Flood Control Work Under Special Authorization


Flood control activities pursuant to Section 205, PL 858, 80th Congress, as amended:

No Section 205 work was performed in Fiscal Year 1996.

Emergency flood control activities-repair, flood fighting, and rescue work (PL 99, 84th Congress, and antecedent legislation):

There were no Federal costs for this fiscal year.

Emergency Bank Protection (Section 14, Flood Control Act of 1946, PL 526, 79th Congress):

Fiscal year costs were $58,040 for continuation of three feasibility studies: 1) The Snake River upstream of Blackfoot, Idaho ($17,718); 2) Fort Hall Landmark, Idaho ($13,234); 3) Willow Creek downstream of LaCrosse, Washington ($8,988); and 4) Little Weiser River, near Gladhart Lane, Idaho ($18,100).

Snagging and clearing of navigable streams and tributaries in interest of flood control (Section 208, Flood Control Act of 1954, PL 780, 83rd Congress):

There were no Federal costs for this fiscal year.

Project modification for the Improvement of the Environment pursuant to Section 1135(b), PL 99-362, as amended:

Fiscal year costs were $260,655 for continuation of five studies and one new study (Soldier Creek, Restoration, Idaho) and initial appraisal and coordination funds, including: 1) Initial Appraisals, General ($5,006); Coordination Account ($3,931); Catherine Creek, Oregon ($29,409); Jackson Hole, Wyoming ($1,620); Little Weiser River, Idaho ($97,597); Portneuf River, Pocatello, Idaho ($57,752); Soldier Creek, Idaho ($6,879); and Walla Walla River, Oregon/Washington ($58,461).