US Army Corps of Engineers
Walla Walla District

Report of the Secretary of the Army
on Civil Works Activities for Fiscal Year 1999

Department of the Army Corps of Engineers
Extract Report of the Walla Walla District

Table 30-K
Snake River Downstream from Johnson Bar Landing, Oregon, Washington, and Idaho
(See Section 15 of Text)


Project Estimated Cost
(Corps of
Engineers
Funds Only)
New Work to
September 30, 1999
Maintenance to
September 30, 1999
Percent
Completed
Const
Started
Approp. Cost Approp. Cost
Ice Harbor Lock and Dam
Initial Project
Code 710 Rec Facilities
Power Units 4-6
Fish Bypass Program
$129,578,480
914,256
36,748,021
85,397,0003
$129,578,4804
914,256
36,748,021
38,762,000
$129,578,4804
914,256
36,748,021
38,762,000
$152,409,912
0
0
0
$152,308,096
0
0
0
100
100
100
45
FY 56
FY 57
FY 71
FY 91
252,637,757 206,002,7574 206,002,7574 152,409,912 152,308,096 82
Little Goose Lock and Dam
Initial Project
Power Units 4-6
Fish Bypass Program
160,413,215
60,941,807
94,341,0003
160,413,2155
60,941,807
35,262,000
160,413,215
60,941,807
33,380,000
105,317,111
0
0
105,095,328
0
0
100
100
35
FY 63
FY 74
FY 89
315,696,022 256,617,0225 254,735,0225 105,317,111 105,095,328 81
Lower Granite Lock and Dam
Initial Project
Code 710 Rec Facilities
Power Units 4-6
Fish Bypass Program
321,503,981
63,800
46,212,534
107,454,0003
321,503,9816
63,800
46,212,534
30,430,000
321,503,9796
63,800
46,212,534
30,330,000
147,551,006
0
0
0
147,436,033
0
0
0
100
100
100
28
FY 65
FY 84
FY 74
FY 88
475,234,315 398,210,3156 398,110,3136 147,551,006 147,436,033 84
Lower Monumental Lock and Dam
Initial Project
Power Units 4-6
Fish Bypass Program
184,712,361
51,661,371
109,241,000
184,712,3617
51,661,371
31,270,0009
184,712,3617
51,661,371
31,270,000
107,286,199
0
0
107,115,132
0
0
100
100
29
FY 61
FY 75
FY 90
345,614,7323 267,643,732 267,643,732 107,286,199 107,115,132 77
Open River
Lewiston to Johnson Bar Landing
34,613 34,6131 34,613 401,5832 397,498
Open River
Pasco to Lewiston
0 0 0 4,350 4,350
Totals Existing Project 1,389,217,439 1,128,508,439 1,126,526,437 512,970,161 512,356,437 74
Previous Projects
Pasco to Lewiston
400,150 400,150 400,150 186,570 186,570
Totals Authorized Project
1,389,617,589 1,128,908,5898 1,126,926,5873 513,156,731 512,543,007
1New work appropriations used for maintenance prior to 1953.
2Includes $2,064 appropriated and $3,180 expended in FY 96 for project condition survey cost.
3Does not include mitigation analysis.
4Includes $203,000 appropriated and $201,931 expended for Columbia River Fish Mitigation Program.
5Includes $370,000 appropriated and $358,589 expended for Columbia River Fish Mitigation Program.
6Includes $1,628,000 appropriated and $1,626,084 expended for Columbia River Fish Mitigation Program.
7Includes $11,132,000 appropriated and $10,949,493 expended for Columbia River Fish Mitigation Program.
8Includes $13,333,000 appropriated and $13,136,097 expended for Columbia River Fish Mitigation Program.