US Army Corps of Engineers
Walla Walla District Website

News Releases by Month

September 2020 (1)
August 2020 (5)
July 2020 (9)
June 2020 (5)
May 2020 (6)
April 2020 (3)
March 2020 (9)
February 2020 (7)
January 2020 (2)
December 2019 (4)
November 2019 (5)
October 2019 (2)
September 2019 (5)
August 2019 (8)
July 2019 (13)
June 2019 (12)
May 2019 (21)
April 2019 (18)
March 2019 (8)
February 2019 (13)
January 2019 (6)
December 2018 (4)
November 2018 (5)
October 2018 (7)
September 2018 (15)
August 2018 (18)
July 2018 (15)
June 2018 (13)
May 2018 (14)
April 2018 (10)
March 2018 (10)
February 2018 (14)
January 2018 (4)
December 2017 (4)
November 2017 (8)
October 2017 (4)
September 2017 (10)
August 2017 (14)
July 2017 (5)
June 2017 (9)
May 2017 (15)
April 2017 (12)
March 2017 (26)
February 2017 (6)
January 2017 (12)
December 2016 (12)
November 2016 (6)
October 2016 (6)
September 2016 (8)
August 2016 (9)
July 2016 (8)
June 2016 (16)
May 2016 (10)
April 2016 (8)
March 2016 (7)
February 2016 (6)
January 2016 (1)
December 2015 (1)
November 2015 (5)
October 2015 (5)
September 2015 (12)
August 2015 (8)
July 2015 (6)
June 2015 (8)
May 2015 (5)
April 2015 (4)
March 2015 (9)
February 2015 (8)
January 2015 (7)
December 2014 (4)
November 2014 (11)
October 2014 (5)
September 2014 (12)
August 2014 (10)
July 2014 (9)
June 2014 (6)
May 2014 (12)
April 2014 (6)
March 2014 (10)
February 2014 (9)
January 2014 (3)
December 2013 (3)
November 2013 (4)
October 2013 (6)
September 2013 (7)
August 2013 (5)
July 2013 (8)
June 2013 (4)
May 2013 (13)
April 2013 (5)
March 2013 (8)
February 2013 (9)
January 2013 (5)
December 2012 (6)
November 2012 (8)
October 2012 (7)
September 2012 (8)
August 2012 (6)
July 2012 (8)
June 2012 (14)
May 2012 (16)
April 2012 (13)
March 2012 (12)
February 2012 (8)
January 2012 (3)
December 2011 (6)
November 2011 (7)
October 2011 (13)
September 2011 (14)
August 2011 (11)
July 2011 (11)
June 2011 (35)
May 2011 (21)
April 2011 (11)
March 2011 (9)
February 2011 (20)
January 2011 (7)

17-051 Mill Creek Levee phase-2 maintenance relocates to north levee bank; trails will temporarily close for visitor safety

Published April 14, 2017
WALLA WALLA, Wash. – The paved trail on the north side of the federally managed section of the Mill Creek Levee System will be temporarily closed to all visitors starting Monday, April 17, to accommodate levee-maintenance activities, U.S. Army Corps of Engineers officials announced today.

Phase-2 of restoring the federally managed portion of the Mill Creek Levee System includes removing tree roots that intruded into the levee cross section from the landside slope. District Geotechnical Section engineers (levee experts) examined several test pits excavated at various points along the mile-long levee and determined removing problematic roots would require “grubbing” roughly two feet into the levee. In some locations, where tree roots have extended deeper into the levee cross section, more extensive excavation and repairs may be required.

Because of unusually severe winter weather which delayed south-levee work progress, Winter-Spring Fiscal Year 2017 repair work on the north levee will begin with an area downstream from the division works near the Mill Creek Office, and progress about 1,525 feet upstream along the levee. Repair and maintenance work on this section will involve heavy equipment and is anticipated to take approximately two weeks to complete, depending upon favorable weather conditions. Repair work on the north levee is being planned to continue during the Fall-Winter period of Fiscal Year 2018.

For visitor safety, temporary closure of portions of the trail will be required while work is in progress. Foot bridges across Mill Creek will be intermittently closed as work progresses along the levee. A map showing the temporary trail closures is available on the Corps’ website at www.nww.usace.army.mil/Missions/Projects/MillCreekLeveeMaintenance.aspx.

Construction fencing will be placed to alert visitors to the temporary closures and encourage public safety. Workers will be accessing the levee with heavy equipment and vehicles to remove the tree roots and recompact levee material.

Walla Walla District will continue to announce work progress and temporary impacts to visitor access. Visitors are also encouraged to look for trail-closure updates on information kiosks located at major trailheads and on the Mill Creek Project’s Facebook page www.facebook.com/millcreekdam.

This maintenance is necessary to meet National Levee Safety Program requirements in accordance with Corps headquarters regulations and policies.
-30-

Contact
Public Affairs Office
509-527-7020
cenww-pa@usace.army.mil

Release no. 17-051