How to Submit Comments. To submit comments via email, cut and paste the email address of the respective Project Manager's from the table below into an email and in the subject line of your email enter: Public Notice Comments for (referencing the specific project).  To submit comments in writing, send them to the respective Project Manager at the U.S. Army Corps of Engineers, Walla Walla District Regulatory Division, 720 E. Park Blvd., Suite 245, Boise, ID 83712. All comments should include the permit application number and project name, your name, address, and phone number.

Public Notice: Application for Permit - NWW-2022-00102 - Sawtooth Lake Mixed-Use Subdivision

WALLA WALLA DISTRICT REGULATORY DIVISION
Published March 29, 2023
Expiration date: 4/13/2023

The Walla Walla District Regulatory Division previously provided a public notice for this Application for Permit on March 24, 2022.  However, the applicant has since changed, requiring a new Public Notice.

Activities of the proposed project remain the same. Information in the public notice has been updated to reflect the status of multiple coordination processes.

Comments received as part of the prior public notice will be carried forward and considered in the current evaluation. There is no need to re-submit comments if you previously commented.

 

Interested parties are hereby notified that the Walla Walla District has received an application for a Department of the Army permit for certain work in Waters of the United States, including wetlands, as described below in the attached documents:

APPLICANT:  Mr. Casey Ames, Basileia Holdings, LLC; 3313 West Cherry Lane, PMB 543 Meridian, Idaho 83642

AGENT: Mr. James Fronk, James Fronk Consulting, LLC; P.O. Box 576 McCall, Idaho 83638

U.S. ARMY CORPS OF ENGINEERS PROJECT MANAGER: Sarah Windham, 720 E. Park Center Blvd. Suite 245, Boise Idaho 83712. Telephone: (208) 433-4469. Email sarah.v.windham@usace.army.mil

PURPOSE:  The purpose of the proposed project is to construct a mixed-use development consisting of single family residential and commercial lots within the City of Middleton.

WATERWAY: Wetlands adjacent to the Boise River.

LOCATION:  The proposed Sawtooth Lake Mixed-Use Subdivision project would be located at 22457 Middleton Road within Section 1, Township 4 North, Range 3 West, near latitude 43.697º N and longitude –116.616º W, in Canyon County, in Middleton, Idaho.  

AUTHORITY:  This permit will be issued or denied under the authority of Section 404 of the Clean Water Act (33 U.S.C. 1344).  A Department of the Army permit is required for the discharge of dredged or fill material into waters of the United States, including wetlands.

WORK: Proposed discharge of 2,650 cubic yards of earthen fill material within approximately 1.64 acres of Palustrine Emergent (PEM) wetlands adjacent to the Boise River.

Specifically, proposed discharges would occur within four (4) wetland areas:

Wetland area one and two entails 0.06 acres of PEM wetland along the western border of the development which drains to the west.

Wetland area three entails 0.27 acres of PEM wetlands along the southwest boundary of the development footprint and is part of a larger wetland that drains to the west.

Wetland area four entails 1.31 acres of PEM wetlands within the western portions of the proposed development and is an enclosed basin. It should be noted that this feature was a constructed feedlot sedimentation basin which was abandoned in the early 2000’s and has developed wetland conditions.

ADDITIONAL INFORMATION: Additional work will occur within the proposed compensatory mitigation sites, located along the southern boundary of the development, as part of the creation and enhancement of unimpacted wetlands within the property. Work may include minor grading, invasive plant removal, planting of vegetation, and removal of old fills, trash and other items. 

CONSTRUCTION PERIOD:  Applicant proposes to start construction in October 2023.  The permit would authorize construction for a period of 5 years.

PROPOSED MITIGATION:  The applicant proposes the following mitigation measures to avoid, minimize, and compensate for impacts to Waters of the United States from activities involving discharges of dredged or fill material. 

The project was designed to limit impacts to aquatic resources by developing within previously identified uplands, and to concentrate additional development fills within impacted and degraded features within the property (i.e., constructed features or fragmented wetlands).

The proposed compensatory mitigation plan consists of permittee-responsible on-site in-kind, mitigation within uplands and previously impacted and degraded wetlands adjacent to the Boise River within the property. The conceptual plan intends to utilize the remaining southern portions of the property to construct 0.7 acres of Palustrine Scrub-Shrub (PSS) and 0.3 acres of PEM which will connect and overlap with existing PSS and PEM wetlands. Existing wetlands will be enhanced by removing historical dumps, invasive species, targeted grading, and vegetation plantings. In addition, a small pond will be created within the Mitigation Area, however this acreage will not be included as mitigation.

The proposal includes the construction of 1 acre of new wetlands and the enhancement of 0.43 acres of wetlands. The targeted wetlands are proposed to consist of higher value and functions than impacted wetlands resulting in an overall functional replacement of greater than 1:1. Influencing factors for the proposal include being located within the floodway, increased vegetation complexity, and adjacency to forested wetland and riparian habitat of the Boise River.

OTHER ENVIRONMENTAL DOCUMENTS AND DA PERMITS ISSUED TO APPLICANT:  An Approved Jurisdictional Determination (AJD) was issued for the north and south parcels along Sawtooth Lake on 28 February 2017 (DA Number NWW-2016-00587). Wetlands identified within the project area were determined to be jurisdictional at that time. A new AJD was completed for the southern property on 21 December 2020, under the Navigable Waters Protection Rule (NWPR). At that time, it was found that the constructed sedimentation basin (Wetland Area four) was not a waters of the United States and would not require a permit to discharge fill material within. The NWPR has since been vacated by the Courts and can no longer be relied upon for permitting. The application has been revised to include previously excluded features.    

WATER QUALITY CERTIFICATION:  A Department of the Army permit will not be issued until water quality certification has been issued or waived by the Idaho Department of Environmental Quality (IDEQ), as required by Section 401 of the Clean Water Act.  The IDEQ evaluated whether the discharge of dredge and/or fill material proposed for this project will not violate existing water quality standards and issued an individual water quality certification on July 15, 2022. Comments concerning Water Quality Certification for this project should be mailed to:  Idaho Department of Environmental Quality, Boise Regional Office, Boise, Idaho 83706.

SECTION 401 (A)(2) NEIGHBORING JURISDICTION:  Per 33 CFR 325(b)(1)(i), the Environmental Protection Agency was provided a copy of IDEQ’s individual water quality certification on July 19, 2022; EPA’s 30-day review period under Section 401(a)(2) ended on August 18, 2022. 

AQUATIC RESOURCE DESCRIPTION:  The project area is located north of the Boise River and west of the Middleton Road Bridge. The general area was historically manipulated for agricultural uses to include construction of drainages, a sediment pond, historical excavation, discharges, and other uses. Current uses within the property are limited to dispersed pedestrian access along the river. Delineated uplands within the development footprint were filled and graded to targeted elevations in 2017.

Previous hydrology studies for the overall property included the installation of piezometers. Data gathered demonstrated that wetlands are generally influenced through shallow subsurface flow from the Boise River, and aerial imagery shows inundation within wetland areas during typical years. However, delineated wetlands within the review area generally do not receive surficial flow over top of bank from the Boise River until flows are above 7000 cubic feet per second, which only occurs during high-water years.

Wetlands within the footprint of the historical feedlot/livestock holding areas appear to have been excavated to a depth to catch run-off from adjacent holding areas and includes a drainage swale to the south that allowed flows into the basin. This area is isolated by levees and berms which extend several feet higher than relative grade, except for the drainage swale which flows to the basin. These features exist generally in the same location and extent as they were in historical imagery since the 1980’s. It is unknown if this area was historically wetlands prior to manipulation. Wetlands within this feature are generally monotype emergent wetlands dominated by cattails, with poison hemlock and grasses along the fringe. 

Other wetlands within the property generally consist of emergent grasses dominated by Reed Canary Grass and Poison Hemlock, and scrub shrub areas typically include False Indigo, with other non-dominant species interspersed throughout.  

The affected wetlands are separated by an existing earthen road/path from riparian forested wetlands abutting the Boise River which include Black Cottonwood, Willow, and other species. No work is proposed within these wetlands.

Wetland area four is an enclosed basin; this feature was a constructed feedlot sedimentation basin which was abandoned in the early 2000’s and has developed wetland conditions.

ANTICIPATED IMPACTS ON AQUATIC ENVIRONMENT:  Impacts from the proposed project will result in direct adverse impacts resulting in a permanent loss of wetlands within the development footprint. These impacts are associated with the filling of approximately 1.64 acres of wetlands. These wetlands area generally low functioning, degraded features historically utilized in part for agricultural purposes.

Beneficial direct impacts may occur within the remaining wetlands within and adjacent to the property as part of the Conceptual Mitigation Plan, which includes enhancement and expansion of wetland types and diversity. Beneficial indirect effects may occur to the riparian wetlands abutting the Boise River, as aquatic resources are consolidated and developed into a larger contiguous riparian corridor.

CULTURAL RESOURCES:  Coordination was conducted with the Idaho State Historic Preservation Office to determine if this activity will affect a site that is listed on the National Register of Historic Places, or a site that may be eligible for listing on the Register. The applicant submitted a cultural resource survey for the project, dated April 2022, and a supplemental evaluation, dated June 7, 2022. Coordination with the Idaho State Historic Preservation Office was concluded on September 9, 2022, after the Idaho State Historic Preservation Office concurred that the proposed project actions will result in no historic properties affected (36 CFR 800.4(d)).

TRIBAL TREATY RIGHTS and INTERESTS:  Federal agencies acknowledge the federal trust responsibility arising from treaties, statues, executive orders and the historical relations between the United States and American Indian Tribes.  The federal government has a unique trust relationship with federally recognized American Indian Tribes, including the Shoshone Paiute and the Shoshone Bannock Tribes.  The Corps has a responsibility and obligation to consider and consult on potential effects to Tribal rights, uses and interests.  The Corps further recognizes there may be a need for additional and on-going consultation.    

ENDANGERED SPECIES:  No listed threatened or endangered species or designated critical habitats are known to exist in the project area.  Coordination may be conducted with the U.S. Fish and Wildlife Service (USFWS) to determine if the activity will have any effect on species designated as endangered or threatened under the Endangered Species Act, or their critical habitat, under the Endangered Species Act of 1973 (87 Stat. 844; 16 U.S.C. 1531 et.seq.).   

ESSENTIAL FISH HABITAT:  The Magnuson-Stevens Fishery Conservation and Management Act, as amended by the Sustainable Fisheries Act of 1996, requires all Federal agencies to consult with the National Marine Fisheries Service on all actions or proposed actions, permitted, funded or undertaken by the agency that may adversely affect Essential Fish Habitat (EFH).  No EFH Species are known to use the project area.  Preliminarily, we have determined the described activity would have no effect to EFH.

ENVIRONMENTAL IMPACT STATEMENT:  Preliminary review indicates the proposed activities will not require preparation of an Environmental Impact Statement.  Comments provided will be considered in preparation of an Environmental Assessment. 

EVALUATION:  The decision whether to issue a permit will be based on an evaluation of the probable impact, including cumulative impacts, of the proposed activity on the public interest.  This decision will reflect the national concern for both protection and utilization of important resources.  The benefit which reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments.  All factors which may be relevant to the proposal will be considered, including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, consideration of property ownership and in general, the needs and welfare of the people.  In addition, our evaluation will include application of the EPA Guidelines (40 CFR 230) as required by Section 404(b)(1) of the Clean Water Act. 

CONSIDERATION OF PUBLIC COMMENTS:  The Corps of Engineers is soliciting comments from the general public; Federal, State and local agencies and officials, Tribal entities and other interested parties in order to consider and evaluate the impacts of this proposed activity.  Any comments received will be considered by the Corps of Engineers to determine whether to issue, modify, condition or deny a permit for this proposal.  To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects and the other public interest factors listed above.  Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act.  Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.

PUBLIC HEARING:  Any person may request in writing, within the comment period specified in this notice, that a public hearing be held to consider this proposed activity.  Requests for a public hearing shall state specific reasons for holding a public hearing. A request may be denied if substantive reasons for holding a hearing are not provided or if there is otherwise no valid interest to be served.

COMMENT & REVIEW PERIOD:  Interested parties are invited to provide comments on the proposed activity, which will become a part of the record and will be considered in the final decision. 

Please mail all comments to:

U.S. Army Corps of Engineers
Walla Walla District
Sarah Windham
Boise Regulatory Office
720 Park Boulevard, Suite 245
Boise, Idaho 83712-7757
Sarah.V.Windham@usace.army.mil

Comments should be received no later than the comment due date of April 13, 2023, as indicated on this notice, to receive consideration.

 


E-Notification

 

Stay up to date on our most recent Public Notices.

The Public Notice, drawings, and attachments will be available for you to view, download, and/or print here on our Public Notice home page.

To add or update your information to our E-Notification list, please email us with your updated information, or please fill out one or both forms below for Idaho Counties and/or Idaho Watershed Public Notice Distribution List(s) and email them to us at: wallawallapndistribution@usace.army.mil