US Army Corps of Engineers
Walla Walla District Website

News Releases by Month

September 2020 (5)
August 2020 (5)
July 2020 (9)
June 2020 (5)
May 2020 (6)
April 2020 (3)
March 2020 (9)
February 2020 (7)
January 2020 (2)
December 2019 (4)
November 2019 (5)
October 2019 (2)
September 2019 (5)
August 2019 (8)
July 2019 (13)
June 2019 (12)
May 2019 (21)
April 2019 (18)
March 2019 (8)
February 2019 (13)
January 2019 (6)
December 2018 (4)
November 2018 (5)
October 2018 (7)
September 2018 (15)
August 2018 (18)
July 2018 (15)
June 2018 (13)
May 2018 (14)
April 2018 (10)
March 2018 (10)
February 2018 (14)
January 2018 (4)
December 2017 (4)
November 2017 (8)
October 2017 (4)
September 2017 (10)
August 2017 (14)
July 2017 (5)
June 2017 (9)
May 2017 (15)
April 2017 (12)
March 2017 (26)
February 2017 (6)
January 2017 (12)
December 2016 (12)
November 2016 (6)
October 2016 (6)
September 2016 (8)
August 2016 (9)
July 2016 (8)
June 2016 (16)
May 2016 (10)
April 2016 (8)
March 2016 (7)
February 2016 (6)
January 2016 (1)
December 2015 (1)
November 2015 (5)
October 2015 (5)
September 2015 (12)
August 2015 (8)
July 2015 (6)
June 2015 (8)
May 2015 (5)
April 2015 (4)
March 2015 (9)
February 2015 (8)
January 2015 (7)
December 2014 (4)
November 2014 (11)
October 2014 (5)
September 2014 (12)
August 2014 (10)
July 2014 (9)
June 2014 (6)
May 2014 (12)
April 2014 (6)
March 2014 (10)
February 2014 (9)
January 2014 (3)
December 2013 (3)
November 2013 (4)
October 2013 (6)
September 2013 (7)
August 2013 (5)
July 2013 (8)
June 2013 (4)
May 2013 (13)
April 2013 (5)
March 2013 (8)
February 2013 (9)
January 2013 (5)
December 2012 (6)
November 2012 (8)
October 2012 (7)
September 2012 (8)
August 2012 (6)
July 2012 (8)
June 2012 (14)
May 2012 (16)
April 2012 (13)
March 2012 (12)
February 2012 (8)
January 2012 (3)
December 2011 (6)
November 2011 (7)
October 2011 (13)
September 2011 (14)
August 2011 (11)
July 2011 (11)
June 2011 (35)
May 2011 (21)
April 2011 (11)
March 2011 (9)
February 2011 (20)
January 2011 (7)

14-078 Old Mill Creek Office demolition begins Monday; partial parking lot closure to occur

Published Oct. 3, 2014
WALLA WALLA, Wash. – Work to remove the old Mill Creek Project office will require temporary closure of a small portion of the Mill Creek Office parking lot beginning Monday, Oct. 6 through mid-November, U.S. Army Corps of Engineers officials announced today.

The Corps awarded a $222,482 contract to Harry Johnson Plumbing and Excavation, Incorporated, of Walla Walla, Wash., to perform the work. The temporary closure around the old building is necessary to accommodate demolition activities and large construction-type equipment and vehicles.

For safety reasons, visitors are asked to not enter any fenced construction areas along the west side of the parking lot. Other areas of the parking lot will remain open to visitors during this time.

The old office building originated as the dam-tender’s house and soils lab in 1938. The house portion was later removed and the soils lab converted into the Mill Creek Project Office. Through decades of changing staff needs, the old office became a configuration of building additions, parts of which were more than 70-years old. By the turn of the century, it no longer met modern building codes (electrical, ADA, etc.), was not very energy efficient and didn’t meet current operations staff needs (not enough room for staff, storage, working space).

A new Mill Creek Project office was constructed during 2013 and officially opened to the public during a ceremony on April 19, 2013. The new office was designed and built with the environment in mind. With a goal of reaching LEED (Leading in Environmental Engineering Design) silver criteria, many energy-saving and environmentally sustainable features were incorporated into the building project. Some of those features include:

• High-albedo roof – High solar-reflectivity roofing material helps keep the building cooler in the summer. Roof insulation meets an R-rating of 70. The walls, which are two studs thick, feature R-rating- 40 insulation.
• High-efficiency mechanical, electrical and plumbing systems – Geothermal heating/cooling, grey water recycling, low-flow plumbing fixtures and light-detecting automatic dimmers contribute to lower energy and water consumption.
• Motion sensors for lighting control – Lights automatically turn off when a room is unoccupied.
• Operable windows for natural ventilation – A big improvement over the old office, in which bars over the windows prevented opening the windows. The heating and cooling unit can take a break when the weather is nice.
• Green power – Solar panels on the roof offset the cost of using electricity off the grid.
• Non-toxic paint, adhesives, carpet and wood finishes – Safer materials for the environment, staff and visitors.
• Flooring materials made with recycled content – Reducing the amount of materials going to our landfills.
• Drought-tolerant, native landscaping – Plants and shrubs that can naturally survive in our environment without irrigation, fertilizer or pesticides.
• Waste-conscious construction – A majority of the waste generated from construction of this building was recycled or reused.
• Operation of the Mill Creek Dam and Bennington Lake has helped spare the City of Walla Walla an estimated 71-million dollars in prevented flood damages since its completion in 1942.

For more information about Mill Creek Dam and Bennington Lake, call the Mill Creek office at 509-527-7160 or visit their Facebook page at www.facebook.com/millcreekdam.

Contact
Public Affairs Office
509-527-7020
cenww-pa@usace.army.mil

Release no. 14-078