Home > Media > News Releases

News Releases by Month

December 2018 (3)
November 2018 (5)
October 2018 (7)
September 2018 (15)
August 2018 (18)
July 2018 (15)
June 2018 (13)
May 2018 (14)
April 2018 (10)
March 2018 (10)
February 2018 (14)
January 2018 (4)
December 2017 (4)
November 2017 (8)
October 2017 (4)
September 2017 (10)
August 2017 (14)
July 2017 (5)
June 2017 (9)
May 2017 (15)
April 2017 (12)
March 2017 (26)
February 2017 (6)
January 2017 (12)
December 2016 (12)
November 2016 (6)
October 2016 (6)
September 2016 (8)
August 2016 (9)
July 2016 (8)
June 2016 (16)
May 2016 (10)
April 2016 (8)
March 2016 (7)
February 2016 (6)
January 2016 (1)
December 2015 (1)
November 2015 (5)
October 2015 (5)
September 2015 (12)
August 2015 (8)
July 2015 (6)
June 2015 (8)
May 2015 (5)
April 2015 (4)
March 2015 (9)
February 2015 (8)
January 2015 (7)
December 2014 (4)
November 2014 (11)
October 2014 (5)
September 2014 (12)
August 2014 (10)
July 2014 (9)
June 2014 (6)
May 2014 (12)
April 2014 (6)
March 2014 (10)
February 2014 (9)
January 2014 (3)
December 2013 (3)
November 2013 (4)
October 2013 (6)
September 2013 (7)
August 2013 (5)
July 2013 (8)
June 2013 (4)
May 2013 (13)
April 2013 (5)
March 2013 (8)
February 2013 (9)
January 2013 (5)
December 2012 (6)
November 2012 (8)
October 2012 (7)
September 2012 (8)
August 2012 (6)
July 2012 (8)
June 2012 (14)
May 2012 (16)
April 2012 (13)
March 2012 (12)
February 2012 (8)
January 2012 (3)
December 2011 (6)
November 2011 (7)
October 2011 (13)
September 2011 (14)
August 2011 (11)
July 2011 (11)
June 2011 (35)
May 2011 (21)
April 2011 (11)
March 2011 (9)
February 2011 (20)
January 2011 (7)

Bookmark and Share Email Print

Posted 5/13/2016

Release no. 16-026


Contact
CENWW-PA - POC: Gina Baltrusch
509-527-7018
cenww-pa@usace.army.mil

or

Bonneville Power Administration – POC: David Wilson
503-230-5607
dbwilson@bpa.gov

BURBANK, Wash. – An advanced-technology turbine, designed to improve fish passage at federal dams on the Columbia and Snake rivers is being installed at Ice Harbor Lock and Dam in southeast Washington state.
The $58 million project, funded by BPA, calls for runner replacements on two turbines, one fixed-blade, one adjustable, along with fish passageway improvements at Ice Harbor over the next few years. 
The first turbine is set to be operational within 12 to 14 months. The work includes structural modifications to the turbine draft tube exits to improve hydraulic conditions for fish. The contracts also contain options to fabricate and install a third turbine runner. 
The turbine design and installation is a collaboration between contractor, Voith Hydro Inc. of York, Pa., the U.S. Army Corps of Engineers, the Bonneville Power Administration and NOAA Fisheries. Small-scale model testing of the new fixed-blade runner design indicates it may also increase power generation by 3 to 4 percent.
“After 50 years of operation and increasing maintenance requirements, the need to replace the existing turbine runners at Ice Harbor presented the opportunity to pursue new turbine runner designs with fish passage improvement as a priority,” said Kevin Crum, project manager. 
Voith Hydro Inc. used digital and physical models, and multiple design cycles to settle on two styles of high-tech runners, (turbine runners are the parts that rotate in water to generate power). The turbine runners are made of stainless steel to fight water corrosion.

BPA engineer George Brown called the work an “excellent example of collaboration among BPA, the Corps, NOAA and a capable contractor.”

“The key ingredient holding us all together is the goal of creating meaningful improvements to the environmental performance of a critical Northwest power resource,” Brown says. “The efficiency and reliability benefits to the hydroelectric system are an important bonus, stretching the value of the limited water resource.”

Advanced-technology turbines could eventually extend beyond Ice Harbor to replace aging infrastructure at other Columbia and Snake river dams.
The latest monitoring shows that less than 10 percent of all migrating juvenile salmon and steelhead pass through turbines on the Snake river, depending on the dam and the species of fish.  At Ice Harbor Dam that number is between 0.5 to 8.6 percent. 
Most out-migrating fish use surface passage, such as spillway weirs, on their way to the ocean. About 93 to 96 percent of all young salmon and steelhead now survive passage at each dam in the Federal Columbia River Power System.
For more information about the Ice Harbor turbine runner design and other programs to benefit Columbia River salmon and steelhead, please visit the Walla Walla District's homepage and www.salmonrecovery.gov.

About BPA
The Bonneville Power Administration, headquartered in Portland, Ore., is a nonprofit federal power marketer that sells wholesale electricity from 31 federal dams and one nuclear plant to 142 Northwest electric utilities, serving millions of consumers and businesses in Washington, Oregon, Idaho, western Montana and parts of California, Nevada, Utah and Wyoming. BPA delivers power via more than 15,000 circuit miles of lines and 259 substations to 490 transmission customers. In all, BPA markets about a third of the electricity consumed in the Northwest and operates three-quarters of the region’s high-voltage transmission grid. BPA also funds one of the largest fish and wildlife programs in the world, and, with its partners, pursues cost-effective energy savings and operational solutions that help maintain affordable, reliable and carbon-free electric power for the Northwest. www.bpa.gov

###


Burbank fish Improvement Turbine USACE Walla Walla District