US Army Corps of Engineers
Walla Walla District

News Releases by Month

June 2019 (10)
May 2019 (21)
April 2019 (18)
March 2019 (8)
February 2019 (13)
January 2019 (6)
December 2018 (4)
November 2018 (5)
October 2018 (7)
September 2018 (15)
August 2018 (18)
July 2018 (15)
June 2018 (13)
May 2018 (14)
April 2018 (10)
March 2018 (10)
February 2018 (14)
January 2018 (4)
December 2017 (4)
November 2017 (8)
October 2017 (4)
September 2017 (10)
August 2017 (14)
July 2017 (5)
June 2017 (9)
May 2017 (15)
April 2017 (12)
March 2017 (26)
February 2017 (6)
January 2017 (12)
December 2016 (12)
November 2016 (6)
October 2016 (6)
September 2016 (8)
August 2016 (9)
July 2016 (8)
June 2016 (16)
May 2016 (10)
April 2016 (8)
March 2016 (7)
February 2016 (6)
January 2016 (1)
December 2015 (1)
November 2015 (5)
October 2015 (5)
September 2015 (12)
August 2015 (8)
July 2015 (6)
June 2015 (8)
May 2015 (5)
April 2015 (4)
March 2015 (9)
February 2015 (8)
January 2015 (7)
December 2014 (4)
November 2014 (11)
October 2014 (5)
September 2014 (12)
August 2014 (10)
July 2014 (9)
June 2014 (6)
May 2014 (12)
April 2014 (6)
March 2014 (10)
February 2014 (9)
January 2014 (3)
December 2013 (3)
November 2013 (4)
October 2013 (6)
September 2013 (7)
August 2013 (5)
July 2013 (8)
June 2013 (4)
May 2013 (13)
April 2013 (5)
March 2013 (8)
February 2013 (9)
January 2013 (5)
December 2012 (6)
November 2012 (8)
October 2012 (7)
September 2012 (8)
August 2012 (6)
July 2012 (8)
June 2012 (14)
May 2012 (16)
April 2012 (13)
March 2012 (12)
February 2012 (8)
January 2012 (3)
December 2011 (6)
November 2011 (7)
October 2011 (13)
September 2011 (14)
August 2011 (11)
July 2011 (11)
June 2011 (35)
May 2011 (21)
April 2011 (11)
March 2011 (9)
February 2011 (20)
January 2011 (7)

Study determines dam-raise alternative won’t meet cost-benefit requirements; Water Board to consider future study options for flood-risk, water-supply concerns (Joint Agency Release)

Published May 18, 2016

BOISE, Idaho – The U.S. Army Corps of Engineers, Walla Walla District, provided a status update for the Boise River Feasibility Study to the Board’s Water Storage Committee members during a special meeting in Boise, today.

O
ver the past several years, the Corps, in partnership with the Idaho Water Board worked together on the feasibility study to evaluate an array of alternatives to reduce flood risks and increase the amount of water available for use in the Boise River Basin.

The Boise River Feasibility Study team conducted detailed hydrologic and economic modeling and analysis and prepared cost estimates for the alternatives. Based on preliminary results, the solution for both flood risk and water supply needs appeared to be a raise of Arrowrock Dam. Several potential dam height raises were considered. However, the results of more detailed economic benefits-and-cost analyses indicate that the dam-raise alternatives do not generate enough economic benefits to exceed the project costs over a 50-year period of analysis. For the Corps to recommend a solution for this study, the benefit-to-cost ratio must exceed 1.0 -- the benefit-to-cost ratio for a dam-raise alternative was a 0.7.

“The Corps and the Board are partners on this study, and it is important we are able to make a joint and informed decision regarding how we will proceed,” said Corps Project Manager Karen Zelch.

Corps and Board study team members provided Water Storage Committee members with a detailed technical briefing of their findings thus far in the feasibility study. At this point, the options for the future of the study are to terminate the study and finalize work products, or request approval to formulate additional alternatives that may meet the study objectives, Zelch explained.

“It’s important to remember that the results of this study do not mean that the flood-risk within Boise and surrounding communities is low. The Boise River is the highest flood-risk priority in the Corps’ Walla Walla District area of operations,” said District Commander Lt. Col. Timothy Vail. “Evidence shows that, while capable of lessening damages for most minor flood events, the Boise River system of dams does not have the capacity to provide enough protection during less frequent, but more intense, flood events. A single large event could cause up to billions of dollars in damages to Boise infrastructure. Though rare, events of this magnitude are likely to happen in the future."

“If the Board is interested in developing additional alternatives for flood-risk and water-supply options, the Walla Walla District will seek approval from Corps Headquarters to reformulate the study. This will include setting a new schedule and budget,” said Zelch. The feasibility study was authorized to spend $3.5 million, with a 50/50 cost share between the Board and the Corps. Work on the study to date has cost $2.6 million (approximately $1.4 million from the Corps and $1.2 million from the Board).

“There is a significant amount of information from the study and feedback from the community to be considered before any final decisions are made,” said Chuck Cuddy, Idaho Water Resource member and committee chair. “IDWR has many other ongoing and anticipated water-resource studies and projects which may having a bearing on the Board’s decision regarding the Boise GI study’s future.”

-30-


Contact
USACE-Walla Walla District
509-527-7018
cenww-pa@usace.army.mil
Public Affairs Office
or
IDWR Public Relations
208-484-0835
sstuebner@cableone.net
Steve Stuebner

Release no. 16-028