US Army Corps of Engineers
Walla Walla District

News Releases by Month

June 2019 (10)
May 2019 (21)
April 2019 (18)
March 2019 (8)
February 2019 (13)
January 2019 (6)
December 2018 (4)
November 2018 (5)
October 2018 (7)
September 2018 (15)
August 2018 (18)
July 2018 (15)
June 2018 (13)
May 2018 (14)
April 2018 (10)
March 2018 (10)
February 2018 (14)
January 2018 (4)
December 2017 (4)
November 2017 (8)
October 2017 (4)
September 2017 (10)
August 2017 (14)
July 2017 (5)
June 2017 (9)
May 2017 (15)
April 2017 (12)
March 2017 (26)
February 2017 (6)
January 2017 (12)
December 2016 (12)
November 2016 (6)
October 2016 (6)
September 2016 (8)
August 2016 (9)
July 2016 (8)
June 2016 (16)
May 2016 (10)
April 2016 (8)
March 2016 (7)
February 2016 (6)
January 2016 (1)
December 2015 (1)
November 2015 (5)
October 2015 (5)
September 2015 (12)
August 2015 (8)
July 2015 (6)
June 2015 (8)
May 2015 (5)
April 2015 (4)
March 2015 (9)
February 2015 (8)
January 2015 (7)
December 2014 (4)
November 2014 (11)
October 2014 (5)
September 2014 (12)
August 2014 (10)
July 2014 (9)
June 2014 (6)
May 2014 (12)
April 2014 (6)
March 2014 (10)
February 2014 (9)
January 2014 (3)
December 2013 (3)
November 2013 (4)
October 2013 (6)
September 2013 (7)
August 2013 (5)
July 2013 (8)
June 2013 (4)
May 2013 (13)
April 2013 (5)
March 2013 (8)
February 2013 (9)
January 2013 (5)
December 2012 (6)
November 2012 (8)
October 2012 (7)
September 2012 (8)
August 2012 (6)
July 2012 (8)
June 2012 (14)
May 2012 (16)
April 2012 (13)
March 2012 (12)
February 2012 (8)
January 2012 (3)
December 2011 (6)
November 2011 (7)
October 2011 (13)
September 2011 (14)
August 2011 (11)
July 2011 (11)
June 2011 (35)
May 2011 (21)
April 2011 (11)
March 2011 (9)
February 2011 (20)
January 2011 (7)

16-077 Corps prepares for Phase-2 Mill Creek Levee maintenance

Published Oct. 21, 2016
WALLA WALLA, Wash. – Visitors using the gravel trail on the south side of the federally managed section of the Mill Creek Levee System in Walla Walla, Washington, will likely encounter surveyors through the afternoon on Friday, Oct. 21, U.S. Army Corps of Engineers officials at the Mill Creek Project Office announced today.

Workers will be surveying the levee in preparation for Phase-2 of levee maintenance. While the trail will remain open during surveying activities, visitors should be aware of equipment and vehicles in the area.

Phase-2 of restoring the federally managed portion of the Mill Creek Levee System includes removing tree roots that intruded into the levee cross section from the landside slope. District Geotechnical Section engineers (levee experts) examined several test pits excavated at various points along the mile-long levee and determined removing problematic roots would require “grubbing” roughly two feet into the levee. In some locations, where tree roots have extended deeper into the levee cross section, more extensive excavation and repairs may be required.

A contract to perform Phase-2 work was awarded to KEU Inc., of Vancouver, Washington, on Sept. 14, 2016. Because of the large scope of work and a narrow timeframe to accomplish it -- between bird-nesting and flood seasons -- task-orders will be issued during multiple years to conduct work in segments.

Winter 2016-2017 Phase-2 repair work on the south levee will include an area from the division works beginning near the Mill Creek Office, progressing toward the Jones Ditch, just downstream of the wooden pedestrian bridge. Repair and maintenance work involving heavy equipment is slated to begin in early December 2016 and is anticipated to take approximately three months to complete. For visitor safety, intermittent closures of parts of Kingfisher and Whitetail trails may be required during the contract performance period. The value of task orders to be performed during Winter 2016-2017 is about $670,000.

The Walla Walla District will continue to keep the public informed of work progress and temporary impacts to visitor access. Visitors are also encouraged to look for trail-closure updates on information kiosks located at major trailheads and on the Mill Creek Project’s Facebook page www.facebook.com/millcreekdam.

This maintenance is necessary to meet National Levee Safety Program requirements in accordance with Corps headquarters regulations and policies. Phase-1 work began on Oct. 8, 2015, and was completed on Dec. 31, 2015. Problematic vegetation was removed from the surface of the levee slopes and 15-feet landward from the levee’s design toe. Non-compliant vegetation on levees blocks visibility for inspections, access for maintenance, hinders flood-fighting operations, and adds uncertainty to structural performance and reliability, which increases risk to the public. The inability to inspect, maintain and flood fight typically delays emergency response and contributes to the risk of levee failure. Life safety is paramount for the Corps’ operations.

Environmental-compliance documents, maps, photos, videos and other information about this levee-maintenance project is available on the Corps’ website at www.nww.usace.army.mil/Missions/Projects/MillCreekLeveeMaintenance.aspx.

-30-


Contact
Public Affairs Office
509-527-7020
cenww-pa@usace.army.mil

Release no. 16-077