US Army Corps of Engineers
Walla Walla District Website

News Releases by Month

October 2020 (3)
September 2020 (6)
August 2020 (5)
July 2020 (9)
June 2020 (5)
May 2020 (6)
April 2020 (3)
March 2020 (9)
February 2020 (7)
January 2020 (2)
December 2019 (4)
November 2019 (5)
October 2019 (2)
September 2019 (5)
August 2019 (8)
July 2019 (13)
June 2019 (12)
May 2019 (21)
April 2019 (18)
March 2019 (8)
February 2019 (13)
January 2019 (6)
December 2018 (4)
November 2018 (5)
October 2018 (7)
September 2018 (15)
August 2018 (18)
July 2018 (15)
June 2018 (13)
May 2018 (14)
April 2018 (10)
March 2018 (10)
February 2018 (14)
January 2018 (4)
December 2017 (4)
November 2017 (8)
October 2017 (4)
September 2017 (10)
August 2017 (14)
July 2017 (5)
June 2017 (9)
May 2017 (15)
April 2017 (12)
March 2017 (26)
February 2017 (6)
January 2017 (12)
December 2016 (12)
November 2016 (6)
October 2016 (6)
September 2016 (8)
August 2016 (9)
July 2016 (8)
June 2016 (16)
May 2016 (10)
April 2016 (8)
March 2016 (7)
February 2016 (6)
January 2016 (1)
December 2015 (1)
November 2015 (5)
October 2015 (5)
September 2015 (12)
August 2015 (8)
July 2015 (6)
June 2015 (8)
May 2015 (5)
April 2015 (4)
March 2015 (9)
February 2015 (8)
January 2015 (7)
December 2014 (4)
November 2014 (11)
October 2014 (5)
September 2014 (12)
August 2014 (10)
July 2014 (9)
June 2014 (6)
May 2014 (12)
April 2014 (6)
March 2014 (10)
February 2014 (9)
January 2014 (3)
December 2013 (3)
November 2013 (4)
October 2013 (6)
September 2013 (7)
August 2013 (5)
July 2013 (8)
June 2013 (4)
May 2013 (13)
April 2013 (5)
March 2013 (8)
February 2013 (9)
January 2013 (5)
December 2012 (6)
November 2012 (8)
October 2012 (7)
September 2012 (8)
August 2012 (6)
July 2012 (8)
June 2012 (14)
May 2012 (16)
April 2012 (13)
March 2012 (12)
February 2012 (8)
January 2012 (3)
December 2011 (6)
November 2011 (7)
October 2011 (13)
September 2011 (14)
August 2011 (11)
July 2011 (11)
June 2011 (35)
May 2011 (21)
April 2011 (11)
March 2011 (9)
February 2011 (20)
January 2011 (7)

19-100 Update: Needle gate replacement work to affect Mill Creek road access Sept. 25 through Sept. 28

Published Sept. 24, 2019

WALLA WALLA, Wash. – Continuing work to replace the needle gate at the headworks of Yellowhawk Creek at the Division Works Dam will require temporary closure of the road access during business hours from Sept. 25 to 28 according to U.S. Army Corps of Engineers operations officials.

Passage across the bridge over Yellowhawk Creek will be closed to enable a crane and lift operation to occur. The parking lot and pedestrian bridge across Mill Creek at this point will also be closed. Passage will be available after the work shift ends at 6 p.m. each day.

Signs will be posted requesting pedestrian/bike traffic to be aware of the impacted area from the road on the south side of the division works and bridge crossing Mill Creek at the diversion dam. In addition, the contractor may use some nearby staging areas as well.

For safety, visitors should respect all closed areas, and be aware of construction vehicles and trucks traveling along the gravel and paved roads on the project during this period.

For more information about this project or for general information about Mill Creek Dam and Bennington Lake, call the Mill Creek office at 509-527-7160. Rangers encourage visitors to “like” and “follow” Mill Creek Dam and Bennington Lake on Facebook for breaking-news and public-access announcements at www.facebook.com/millcreekdam.


Contact
CENWW-PA
509-527-7020
CENWW-PA@USACE.ARMY.MIL

Release no. 19-100