US Army Corps of Engineers
Walla Walla District Website

News Releases by Month

August 2020 (2)
July 2020 (9)
June 2020 (5)
May 2020 (6)
April 2020 (3)
March 2020 (9)
February 2020 (7)
January 2020 (2)
December 2019 (4)
November 2019 (5)
October 2019 (2)
September 2019 (5)
August 2019 (8)
July 2019 (13)
June 2019 (12)
May 2019 (21)
April 2019 (18)
March 2019 (8)
February 2019 (13)
January 2019 (6)
December 2018 (4)
November 2018 (5)
October 2018 (7)
September 2018 (15)
August 2018 (18)
July 2018 (15)
June 2018 (13)
May 2018 (14)
April 2018 (10)
March 2018 (10)
February 2018 (14)
January 2018 (4)
December 2017 (4)
November 2017 (8)
October 2017 (4)
September 2017 (10)
August 2017 (14)
July 2017 (5)
June 2017 (9)
May 2017 (15)
April 2017 (12)
March 2017 (26)
February 2017 (6)
January 2017 (12)
December 2016 (12)
November 2016 (6)
October 2016 (6)
September 2016 (8)
August 2016 (9)
July 2016 (8)
June 2016 (16)
May 2016 (10)
April 2016 (8)
March 2016 (7)
February 2016 (6)
January 2016 (1)
December 2015 (1)
November 2015 (5)
October 2015 (5)
September 2015 (12)
August 2015 (8)
July 2015 (6)
June 2015 (8)
May 2015 (5)
April 2015 (4)
March 2015 (9)
February 2015 (8)
January 2015 (7)
December 2014 (4)
November 2014 (11)
October 2014 (5)
September 2014 (12)
August 2014 (10)
July 2014 (9)
June 2014 (6)
May 2014 (12)
April 2014 (6)
March 2014 (10)
February 2014 (9)
January 2014 (3)
December 2013 (3)
November 2013 (4)
October 2013 (6)
September 2013 (7)
August 2013 (5)
July 2013 (8)
June 2013 (4)
May 2013 (13)
April 2013 (5)
March 2013 (8)
February 2013 (9)
January 2013 (5)
December 2012 (6)
November 2012 (8)
October 2012 (7)
September 2012 (8)
August 2012 (6)
July 2012 (8)
June 2012 (14)
May 2012 (16)
April 2012 (13)
March 2012 (12)
February 2012 (8)
January 2012 (3)
December 2011 (6)
November 2011 (7)
October 2011 (13)
September 2011 (14)
August 2011 (11)
July 2011 (11)
June 2011 (35)
May 2011 (21)
April 2011 (11)
March 2011 (9)
February 2011 (20)
January 2011 (7)

20-039 Road repaving to begin at Mill Creek as construction projects continue

Published July 24, 2020
Map of Mill Creek and the surrounding area, detailing the construction and the alternate access routes available to the public during the course of road repaving.

Map of Mill Creek and the surrounding area, detailing the construction and the alternate access routes available to the public during the course of road repaving.

Walla Walla, WA -- The U.S. Army Corps of Engineers’ Walla Walla District (Corps) will be repaving Reservoir Road at Mill Creek beginning Aug. 3.

This construction will result in traffic control and road closure to Bennington Lake. There will also be shorter closures leading up to the construction, which will occur on July 29 and 30 during working hours for the Mill Creek Project to complete some preparatory work.

Visitors should be aware that construction will result in delays to access the project office parking area. Driving access to Bennington Lake will be unavailable. In addition to the road work, the division works fish ladder replacement construction is still ongoing and has reduced parking capacity at the project office parking lot. Horseback riders in particular will not have access to park with their trailers during the construction. The nearest available parking to the Bennington Lake area will be either Rooks Park or the Walla Walla Community College Athletic Fields parking lot.

The repaving project will involve grinding down the old road surface, which will then become the base underneath newly placed asphalt. Improvements include the elimination of pot holes and crumbing roads surfaces, replacing speed bumps with wider speed humps that better accommodate trailers, and additional stop signs for increased safety at the project office turn off.

The work to repaving project amounted to a $999,000.00 contract that was awarded to Central Washington Asphalt, which is based out of Milton-Freewater, Oregon.

Additional construction projects taking place over the summer at Mill Creek Dam and Bennington Lake include replacing the downstream fish ladder at the first division works, which is already underway and has closed access to the yellow footbridge over Mill Creek and detoured part of the paved levee trail; Mill Creek Dam rehabilitation, which will result in the closure of portions of Rooks Park; closure of the Mill Creek Project parking lot for maintenance building construction; and restroom installation at Bennington Lake, which will result in the closure of the Bennington Lake parking lot. Almost every aspect of the Mill Creek Dam and Bennington Lake area will be affected by temporary closures throughout the summer.

“It is really great that we are getting so much work accomplished this summer. The added benefit of getting people back to work in these unprecedented times will have positive impact well beyond the boundaries of Mill Creek Dam and Bennington Lake. Unfortunately the timing of the closures happens to be in the same year as closures due to flooding followed by restrictions from COVID-19. Our biggest mission this summer will be to keep visitors informed of the various closure to reduce frustrations people may be feeling about not being able to visit one of the busiest and appreciated recreation areas in the vicinity,” Natural Resources Specialist Jeremy Nguyen said.

More information about upcoming construction will be released once contracts are finalized. More information can also be found on the Mill Creek Facebook page at https://www.facebook.com/millcreekdam/.


Contact
CENWW-PA
509-527-7020
cenww-pa@useace.army.mil

Release no. 20-065